Knowee
Questions
Features
Study Tools

Given the following information, assign overhead costs to Product B using ABC.  ActivityCostsCost DriverAssembling costs$200,000Machine-hoursSetup costs$75,000Number of setupsInspecting costs$50,000Direct labor-hours   ActivityProduct A UseProduct B UseAssembling costs500 machine-hours300 machine-hoursSetup costs10 setups15 setupsInspecting costs25 direct labor-hours15 direct labor-hoursMultiple choice question.$138,750$125,250$150,750

Question

Given the following information, assign overhead costs to Product B using ABC.  ActivityCostsCost DriverAssembling costs200,000MachinehoursSetupcosts200,000Machine-hoursSetup costs75,000Number of setupsInspecting costs50,000Directlaborhours   ActivityProductAUseProductBUseAssemblingcosts500machinehours300machinehoursSetupcosts10setups15setupsInspectingcosts25directlaborhours15directlaborhoursMultiplechoicequestion.50,000Direct labor-hours   ActivityProduct A UseProduct B UseAssembling costs500 machine-hours300 machine-hoursSetup costs10 setups15 setupsInspecting costs25 direct labor-hours15 direct labor-hoursMultiple choice question.138,750125,250125,250150,750

...expand
🧐 Not the exact question you are looking for?Go ask a question

Solution

To assign overhead costs to Product B using Activity-Based Costing (ABC), we first need to determine the cost per unit of each activity (cost driver). Then, we multiply the cost per unit by the number of units used by Product B.

  1. Assembling costs: The total cost is 200,000andthecostdriverismachinehours.So,thecostpermachinehouris200,000 and the cost driver is machine-hours. So, the cost per machine-hour is 200,000 / (500 machine-hours for Product A + 300 machine-hours for Product B) = 200,000/800machinehours=200,000 / 800 machine-hours = 250 per machine-hour. For Product B, the assembling costs are 300 machine-hours * 250permachinehour=250 per machine-hour = 75,000.

  2. Setup costs: The total cost is 75,000andthecostdriveristhenumberofsetups.So,thecostpersetupis75,000 and the cost driver is the number of setups. So, the cost per setup is 75,000 / (10 setups for Product A + 15 setups for Product B) = 75,000/25setups=75,000 / 25 setups = 3,000 per setup. For Product B, the setup costs are 15 setups * 3,000persetup=3,000 per setup = 45,000.

  3. Inspecting costs: The total cost is 50,000andthecostdriverisdirectlaborhours.So,thecostperdirectlaborhouris50,000 and the cost driver is direct labor-hours. So, the cost per direct labor-hour is 50,000 / (25 direct labor-hours for Product A + 15 direct labor-hours for Product B) = 50,000/40directlaborhours=50,000 / 40 direct labor-hours = 1,250 per direct labor-hour. For Product B, the inspecting costs are 15 direct labor-hours * 1,250perdirectlaborhour=1,250 per direct labor-hour = 18,750.

Adding up these costs, the total overhead costs assigned to Product B using ABC are 75,000(assembling)+75,000 (assembling) + 45,000 (setup) + 18,750(inspecting)=18,750 (inspecting) = 138,750. So, the correct answer is $138,750.

This problem has been solved

Similar Questions

Given the following information, compute the cost driver rate for assembling costs.  ActivityCostsCost DriverAssembling costs$200,000Machine-hoursSetup costs$75,000Number of setupsInspecting costs$50,000Direct labor-hours   ActivityProduct A UseProduct B UseAssembling costs500 machine-hours300 machine-hoursSetup costs10 setups15 setupsInspecting costs25 direct labor-hours15 direct labor-hoursMultiple choice question.$400 per machine-hour$133 per machine-hour$250 per machine-hour$667 per machine-hour

Multiple Choice QuestionJohnson Company has the following overhead costs: machine setup $25,000; factory services $10,000; design of $15,000; and selling expenses of $5,000. What is the total overhead costs using activity-based costing?Multiple choice question.$50,000.$40,000.$20,000.$55,000.

Fill in the Blank QuestionFill in the blank question.A company has the following activities and costs: machine setup of $5,000 per setup and factory services of $100 per square foot.  If product 1 uses 2 setups and has 10,000 square feet, overhead allocated to product 1 is $.

Multiple Choice QuestionJackson Company uses activity-based costing to allocate their overhead costs. Setup costs of $850,000 are based on number of batches. Design modification costs of $155,000 are based on number of design changes. Jackson Company has identified 40,000 batches and has 5,000 design changes in their factory. What is the activity rate for setup.Multiple choice question.$3.88$21.25$25.13$31.00

Multiple Choice QuestionSpring Company uses activity-based costing to allocate their overhead costs. Setup costs of $100,000 are based on number of setups. Factory services of $65,000 are based on square footage. Spring Company has identified 500 setups and has 10,000 square feet in their factory. What is the activity rate for the setup activity cost pool.Multiple choice question.$330.00$16.50$6.50$200.00

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.