In a CPM/PERT network the critical path is the:Group of answer choicesshortest (duration) path through the network.lowest path through the network.longest (duration) path through the network.highest path through the network.
Question
In a CPM/PERT network the critical path is the:Group of answer choicesshortest (duration) path through the network.lowest path through the network.longest (duration) path through the network.highest path through the network.
Solution
In a CPM/PERT network, the critical path is the longest (duration) path through the network.
Similar Questions
The critical path is the _____ path through a network diagram, and it represents the _____ amount of slack or float.Group of answer choiceslongest; shortestlongest; longestshortest; shortestshortest; longest
What is the critical path?
The critical pathIs a path that operates from the starting node to the end nodeIs a mixture of all paths.Is the longest pathIs the shortest path
hile solving a network flow problem by PERT, which of the followingtype of time will be used to measure the length of Critical Path? Pessimistic Expected Most Likely Optimistic
Which of the following are some steps to create a critical path? Select all that apply.1 pointMake time estimates.Consult your main customer.Create a network diagram.Set dependencies.
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.