Which of the following are some steps to create a critical path? Select all that apply.1 pointMake time estimates.Consult your main customer.Create a network diagram.Set dependencies.

Question

Which of the following are some steps to create a critical path? Select all that apply.1 pointMake time estimates.Consult your main customer.Create a network diagram.Set dependencies.

🧐 Not the exact question you are looking for?Go ask a question

Solution

The steps to create a critical path from the options provided are:

  1. Make time estimates.
  2. Create a network diagram.
  3. Set dependencies.

Consulting your main customer is not typically a step in creating a critical path.

Similar Questions

Critical path method is suitable for _____________ project schedulesa.Optimizingb.Minimisingc.Maximizationd.None of the given options

In a CPM/PERT network the critical path is the:Group of answer choicesshortest (duration) path through the network.lowest path through the network.longest (duration) path through the network.highest path through the network.

When creating a critical path, what does a network diagram help visualize? Select all that apply.1 pointWhich skilled teammate can work on each taskThe path of work from the start to the end of the projectWhich non-essential tasks are not on the critical pathThe tasks that can be performed in parallel

What is the critical path?

A construction project is modeled by the activity network given below. The activities are represented by the arcs and the numbers in brackets on each arc represents the time (in days) to complete the activity. Each activity requires one worker. The project is to be completed in the shortest time.I. Using the network provided, calculate the earliest time and latest time for each activity. [8]II. State the critical activities and identify the critical path(s). [3]III. Find the total float of activities D and F. You must show your working. [3]IV. Explain why it is important for a project manager to use float in project management? [3]