Select the correct answerA can do a piece of work in 5 days, B can do it in 10 days. With the help of C, they finish the work in 2 days. In how many days C alone can do the whole work?Options3 days5 days6 days4 days
Question
Select the correct answerA can do a piece of work in 5 days, B can do it in 10 days. With the help of C, they finish the work in 2 days. In how many days C alone can do the whole work?Options3 days5 days6 days4 days
Solution
To solve this problem, we first need to find the rates at which A, B, and C work.
- A can do the work in 5 days, so A's work rate is 1/5 of the work per day.
- B can do the work in 10 days, so B's work rate is 1/10 of the work per day.
- Together, A, B, and C can do the work in 2 days, so their combined work rate is 1/2 of the work per day.
We can find C's work rate by subtracting A and B's work rates from the combined work rate:
C's work rate = (A + B + C)'s work rate - A's work rate - B's work rate C's work rate = 1/2 - 1/5 - 1/10 = 1/2 - 2/10 - 1/10 = 1/2 - 3/10 = 2/10 = 1/5
So, C can do 1/5 of the work per day, which means C can do the whole work in 5 days. Therefore, the correct answer is "5 days".
Similar Questions
A can do a piece of work in 5 days and B in 20 days. They work together for 2 days and then both leave the work. Then C alone can finish the remaining work in 6 days. In how many days will C finish the full work?
Select the correct answerA can finish one-third of a work in 5 days, B can finish 2/5th of the same work in 10 days and C can finish 75% of the same work in 15 days. They work together for 6 days; The remaining work will be finished by B alone in?Options3 days5 days2.5 days1.5 days
Select the correct answerA and B together can do a piece of work in 12 days which B and C together do in 16 days. If A works for 5 days, B works for 7 days than C completes the remaining work in 13 days. In how much time B alone does the whole work?Options48 days16 days24 days12 days
Select the correct answerA can complete 1/3 of a work in 5 days and B, 2/5 of the work in 10 days. In how many days both A and B together can complete the work?Options7 1/2days9 3/8 days10 days8 4/5days
Select the correct answerA can complete a piece of work in 15 days and B alone can do it in 10 days. B works at it for 5 days and then leaves. In how many days, A alone can finish the remaining work?Options7 days8 days8.5 days7.5 days