A can build up a wall in 8 days while B can break it in 3 days. A has worked for 4 days and then B joined to work with A for another 2 days only. In how many days will A alone build up the remaining part of the wall?Options13 days7 1/3 days13 1/3 days7 days
Question
A can build up a wall in 8 days while B can break it in 3 days. A has worked for 4 days and then B joined to work with A for another 2 days only. In how many days will A alone build up the remaining part of the wall?Options13 days7 1/3 days13 1/3 days7 days
Solution
To solve this problem, we first need to understand the rate at which A and B work.
- A can build a wall in 8 days. So, A's work rate is 1 wall/8 days = 1/8 of the wall per day.
- B can break a wall in 3 days. So, B's work rate is -1 wall/3 days = -1/3 of the wall per day (negative because B is breaking the wall).
Next, we calculate how much of the wall is built after A works for 4 days and then A and B work together for 2 days.
- In 4 days, A can build 4 * (1/8) = 1/2 of the wall.
- When A and B work together, their combined work rate is (1/8 - 1/3) = -1/24 of the wall per day. So, in 2 days, they can build 2 * (-1/24) = -1/12 of the wall. Since this is negative, it means that they actually break 1/12 of the wall.
So, after 6 days (4 days of A working and 2 days of A and B working together), 1/2 - 1/12 = 5/12 of the wall is built.
Finally, we calculate how long it will take A to build the remaining part of the wall.
- The remaining part of the wall is 1 - 5/12 = 7/12.
- Since A's work rate is 1/8 of the wall per day, it will take A (7/12) / (1/8) = 7 * (8/12) = 56/12 = 4 2/3 days to build the remaining part of the wall.
So, the answer is 4 2/3 days. However, this option is not available in the given options. There might be a mistake in the problem or the options.
Similar Questions
A can do a piece of work in 8 days and B can do the same work in 10 days. They started the work together but after 3 days, A left . In how many days B can complete the remaining work?4 days7 days7.5 days3. 25 days
A and B together can finish a work in 6.75 days. A alone can finish the same work in 9 days. In how many days will B alone finish the work?Options18 days27 days35 days36 days
A started a work and left after working for 2 days. Then B was called and he finished the work in 9 days. Had A left the work after working for 3 days, B would have finished the remaining work in 6 days. In how many days can each of them, working alone finish the whole work?Options2.5 days, 7.5 days5 days, 8.5 days5 days, 15 daysNone of these
A and B can do a piece of work in 6 2/3 days and 5 days respectively. They work together for 2 days and then A leaves. In how many days after that B will complete the work alone.a.3 ½ daysb.2 daysc.1 ½ daysd.3 days
A and B can build a certain wall in 20 days and 30 days respectively. In how many days can they together build two such walls?
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.