If Task A must be completed before task B can begin, select the correct design from the following: A. task A has a sequence flow coming out of it to task B B. task A connects via sequence flow to a parallel gateway, then to task B C. task A's completion triggers a timer event, which allows task B to begin D. tasks A and B are connected by a message flow E. none of the above

Question

If Task A must be completed before task B can begin, select the correct design from the following: A. task A has a sequence flow coming out of it to task B B. task A connects via sequence flow to a parallel gateway, then to task B C. task A's completion triggers a timer event, which allows task B to begin D. tasks A and B are connected by a message flow E. none of the above

🧐 Not the exact question you are looking for?Go ask a question

Solution

The correct design from the given options is A. Task A has a sequence flow coming out of it to task B. This design indicates that Task B can only begin after Task A has been completed, which is the requirement stated in the question.

Similar Questions

As a project manager, you’re identifying task dependencies. Task B cannot finish until Task A has started. Which type of dependency does this situation represent? 1 pointStart to Finish (SF)Finish to Finish (FF)Finish to Start (FS)Start to Start (SS)

Continuing with the construction project scenario from the previous question, the project team completes the designs (Task A) and then begins construction (Task B). What type of dependency describes the relationship between Tasks A and B?1 pointStart-to-Start (SS)Start-to-Finish (SF)Finish-to-Finish (FF)Finish-to-Start (FS)

T1 must be done during T3T2 must be achieved before T1 startsT2 must overlap with T3T4 must start after T1 is complete• Are the constraints compatible?T1T2T3T4

Which is the name of the Task which comes before the current task?Question 8Select one:a.Successorb.Critical Pathc.Predecessord.Milestone

When two activities start at the same event and end at the same event, they should be shown by means of a _________Question 3Answera.Projectb.Dummy activityc.Taskd.Task