As a project manager, you’re identifying task dependencies. Task B cannot finish until Task A has started. Which type of dependency does this situation represent? 1 pointStart to Finish (SF)Finish to Finish (FF)Finish to Start (FS)Start to Start (SS)

Question

As a project manager, you’re identifying task dependencies. Task B cannot finish until Task A has started. Which type of dependency does this situation represent? 1 pointStart to Finish (SF)Finish to Finish (FF)Finish to Start (FS)Start to Start (SS)

🧐 Not the exact question you are looking for?Go ask a question

Solution

This situation represents a Start to Finish (SF) dependency. In this type of dependency, Task B (dependent task) cannot finish until Task A (predecessor task) has started.

Similar Questions

Continuing with the construction project scenario from the previous question, the project team completes the designs (Task A) and then begins construction (Task B). What type of dependency describes the relationship between Tasks A and B?1 pointStart-to-Start (SS)Start-to-Finish (SF)Finish-to-Finish (FF)Finish-to-Start (FS)

If Task A must be completed before task B can begin, select the correct design from the following: A. task A has a sequence flow coming out of it to task B B. task A connects via sequence flow to a parallel gateway, then to task B C. task A's completion triggers a timer event, which allows task B to begin D. tasks A and B are connected by a message flow E. none of the above

Which is the name of the Task which comes before the current task?Question 8Select one:a.Successorb.Critical Pathc.Predecessord.Milestone

A project manager identifies a series of tasks in an upcoming project that can only be started when the previous task has been completed. What term defines the relationship between these tasks? 1 pointStackedConnectedDependencyOpposed

Determining the proper task order will help you assign start and end dates for each task. When determining task priorities, what should you consider first?1 pointThe basic order of operationsThe number of team members available for the projectThe target date for completing the projectWhich team members will address each task