Knowee
Questions
Features
Study Tools

Select the correct answerA’s 2 days’ work is equal to B’s 3 days’ work. If A can complete the work in 8 days then to complete the work B will take?Options14 days15 days16 days12 days

Question

Select the correct answerA’s 2 days’ work is equal to B’s 3 days’ work. If A can complete the work in 8 days then to complete the work B will take?Options14 days15 days16 days12 days

🧐 Not the exact question you are looking for?Go ask a question

Solution

The problem states that A's 2 days of work is equal to B's 3 days of work. This means that B works 2/3 as fast as A.

We know that A can complete the work in 8 days. Since B works 2/3 as fast as A, B will take 1/(2/3) = 1.5 times as long as A to complete the work.

Therefore, B will take 1.5 * 8 = 12 days to complete the work.

So, the correct answer is 12 days.

Similar Questions

Select the correct answerA can complete a work in 12 days, B in 15 days. Find the time taken by them: If A leaves two days before the scheduled completion of the work.Options9 4/79 1/69 5/69 2/3

Select the correct answerAmit can complete a piece of work in 16 days. Rohit can complete the same piece of work in 8 days. If both of them work together in how many days can they complete the same piece of work?Options4 2/5 days6 days12 days5 1/3days

Select the correct answerA can complete a work in 12 days, B in 15 days. When A and B worked alternatively, when started byOptions12 2/5 days11 2/5 days13 3/5 days13 2/5 days

A can do a piece of work in 8 days and B can do the same work in 10 days. They started the work together but after 3 days, A left . In how many days B can complete the remaining work?4 days7 days7.5 days3. 25 days

Select the correct answerA, B and C can do a work separately in 24, 36 and 48 days respectively. B leaves 7 days before completion and A left 3 days before completion. work will finish in how many days?Options11 5/1312 7/1314 8/1313 9/13

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.