Who can change the sprint backlog during a sprint?I.Scrum MasterII.Product Owner III.Development TeamIV.stakeholder

Question

Who can change the sprint backlog during a sprint?I.Scrum MasterII.Product Owner III.Development TeamIV.stakeholder

🧐 Not the exact question you are looking for?Go ask a question

Solution

The Sprint Backlog can be changed during a Sprint by the Development Team. The Scrum Master, Product Owner, and Stakeholders do not have the authority to change the Sprint Backlog once the Sprint has started. This is because the Development Team owns the Sprint Backlog and they are the ones who have committed to completing the work. If there is a need to change the Sprint Backlog due to a change in business requirements or priorities, it should be discussed in the Sprint Review or during the next Sprint Planning.

This problem has been solved

Similar Questions

Who is responsible for prioritizing the product backlog?I.Product OwnerII.Scrum Team III.StakeholderIV.Scrum Master

Which Scrum Role is primarily responsible for owning and updating the Product Backlog?1 pointProduct OwnerScrum MasterHigh-Influence StakeholderDevelopment Team

What is the person called on an Agile team who gets to decide what goes on the sprint backlog and whether a task is done or not?answerManagerTeam leaderProduct ownerMarathon runner

Which scrum role is responsible for the product backlog?1 pointDevelopment team members.Product owner.Scrum master.

Who is typically the owner of the Product Backlog in an Agile project? 1 pointThe stakeholdersThe clientThe Development TeamThe Product Owner