What is the person called on an Agile team who gets to decide what goes on the sprint backlog and whether a task is done or not?answerManagerTeam leaderProduct ownerMarathon runner
Question
What is the person called on an Agile team who gets to decide what goes on the sprint backlog and whether a task is done or not?answerManagerTeam leaderProduct ownerMarathon runner
Solution
The person on an Agile team who gets to decide what goes on the sprint backlog and whether a task is done or not is called the Product owner.
Similar Questions
Who can change the sprint backlog during a sprint?I.Scrum MasterII.Product Owner III.Development TeamIV.stakeholder
Which scrum role is responsible for the product backlog?1 pointDevelopment team members.Product owner.Scrum master.
Who is typically the owner of the Product Backlog in an Agile project? 1 pointThe stakeholdersThe clientThe Development TeamThe Product Owner
Question 4Select the correct statement regarding sprint planning.1 pointThe scrum master describes the goal.The product owner creates new milestones and gives them titles.The development team takes the stories from the top of the product backlog and assigns them to the sprint backlog.The product owner determines the team velocity.
Which of the following is done at the sprint planning meeting?1 pointThe product owner describes the goal.The team agrees to the labels, estimates, and story details.A sprint backlog is created.All of the above.
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.