Suppose two activities A and B, having start and finish time as SA, FA and SB, FB respectively. Both the activities are said to be compatible, under which of the following condition?1 pointSA = FBSA > FBSA >= FB or SB >= FASA >= FB and SB = FA

Question

Suppose two activities A and B, having start and finish time as SA, FA and SB, FB respectively. Both the activities are said to be compatible, under which of the following condition?1 pointSA = FBSA > FBSA >= FB or SB >= FASA >= FB and SB = FA

🧐 Not the exact question you are looking for?Go ask a question

Solution

Two activities A and B, with start and finish times SA, FA and SB, FB respectively, are said to be compatible under the condition that SA >= FB or SB >= FA. This means that one activity should start only after the other activity has finished. This ensures that the activities do not overlap in time, hence they are compatible.

Similar Questions

In a project, Activity A has a duration of four days and begins on the morning of Monday the fourth. The successor Activity, B, has a Finish- to-Start (FS) relationship with A. The Finish-to-Start relationship has two days of lag, and Activity B has a duration of three days. If Saturday and Sunday are non-working days, which of the following statements is true?2 MarksTotal elapsed days (completing both activities) is seven daysActivity B will be completed by the end of the day on Thursday, theActivity B will be completed by the end of the day on Friday, the 15tActivity B will be completed by the end of the day on Tuesday, the 1

Question 5 (10 marks)Activities A to P are part of the set-up of a music festival. The network diagram below shows theseactivities and their completion time in days.G2 J5M4N2E5H2B3A5D4C3F4P3L3K7startfinish(a) Which activity must be on the critical path?(1 mark)A forward and backward scan has been completed on the network diagram below.5 50 03 4 8 813 1317 1715 1722 2219 2124 24G2J5M4N2E5H2B3A5D4C3F4P3L3K717 17startfinish(b) State the critical path(s) for the set-up of the music festival.(2 marks)page 11 of 23 PLEASE TURN OVER(c) Calculate the amount of slack time available for activity L

When two activities start at the same event and end at the same event, they should be shown by means of a _________Question 3Answera.Projectb.Dummy activityc.Taskd.Task

You are given the following activity diagram. Which of the following action sequences are possible during one execution of the activity diagram?Select one or more:A → B → CA → C → BA → CA → B

For a time-constrained project, which of the following activities can be moved on the project timeline?Group of answer choicesCritical activities onlyNon-critical activities onlyBoth critical and non-critical activitesNone of the activities can be moved on the project timeline