In a project, Activity A has a duration of four days and begins on the morning of Monday the fourth. The successor Activity, B, has a Finish- to-Start (FS) relationship with A. The Finish-to-Start relationship has two days of lag, and Activity B has a duration of three days. If Saturday and Sunday are non-working days, which of the following statements is true?2 MarksTotal elapsed days (completing both activities) is seven daysActivity B will be completed by the end of the day on Thursday, theActivity B will be completed by the end of the day on Friday, the 15tActivity B will be completed by the end of the day on Tuesday, the 1

Question

In a project, Activity A has a duration of four days and begins on the morning of Monday the fourth. The successor Activity, B, has a Finish- to-Start (FS) relationship with A. The Finish-to-Start relationship has two days of lag, and Activity B has a duration of three days. If Saturday and Sunday are non-working days, which of the following statements is true?2 MarksTotal elapsed days (completing both activities) is seven daysActivity B will be completed by the end of the day on Thursday, theActivity B will be completed by the end of the day on Friday, the 15tActivity B will be completed by the end of the day on Tuesday, the 1

...expand
🧐 Not the exact question you are looking for?Go ask a question

Solution

Let's break down the activities and their durations:

Activity A:

  • Starts on Monday the 4th
  • Duration of 4 days
  • Therefore, it finishes on Thursday the 7th

Activity B:

  • Has a Finish-to-Start relationship with A, with 2 days of lag
  • Therefore, it starts on Monday the 11th (since Saturday and Sunday are non-working days)
  • Duration of 3 days
  • Therefore, it finishes on Wednesday the 13th

So, the total elapsed days (completing both activities) is 9 days (4 days for Activity A, 2 days of lag, and 3 days for Activity B).

Therefore, the statement "Activity B will be completed by the end of the day on Tuesday, the 1" is incorrect. The correct statement would be "Activity B will be completed by the end of the day on Wednesday, the 13th".

This problem has been solved

Similar Questions

In a development project, if an activity (i,j) of six days duration, starts late on 3rd day then which of thefollowing will be its latest finish time?Select correct option:9th day2nd day3rd day18th day

A and B can finish a work, working on alternate days, in 17 days, where A works on the first day. Similarly, they can finish the work, working on alternate days, in days, where B works on the first day. If C, working alone, can complete the work in 35 days, in how many days can the work be completed when A, B and C work together

A and B can do a piece of work in 6 2/3 days and 5 days respectively. They work together for 2 days and then A leaves. In how many days after that B will complete the work alone.a.3 ½ daysb.2 daysc.1 ½ daysd.3 days

A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in :8 days10 days12 days15 days

A started a work and left after working for 2 days. Then B was called and he finished the work in 9 days. Had A left the work after working for 3 days, B would have finished the remaining work in 6 days. In how many days can each of them, working alone finish the whole work?Options2.5 days, 7.5 days5 days, 8.5 days5 days, 15 daysNone of these

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.