PERT is used for one time projects that involve activities of_________a.Non-repetitive natureb.Repetitive naturec.Continuous natured.Invalid in natur
Question
PERT is used for one time projects that involve activities of_________a.Non-repetitive natureb.Repetitive naturec.Continuous natured.Invalid in natur
Solution
The correct answer is a. Non-repetitive nature. PERT (Program Evaluation Review Technique) is a planning and control tool used for defining and controlling the tasks necessary to complete a project. It is particularly useful for projects where the time required to complete various tasks is unknown and activities are not repetitive.
Similar Questions
What is the full form of PERT?a.Project evaluation and review techniqueb.Programme evaluation and review technique.c.Problem evaluation and review techniqued.Project evaluation and revision technique
PERT is suitable for _____________ project schedules.a.Optimizingb.Minimisingc.Maximizationd.None of the given options
The PERT in project management means program evaluation and _____ technique.
PERT is a three time estimate and gives more weightage toQuestion 3Answera.Optimistic timeb.Most likely timec.Pessimistic timed.Expected time
PERT is use full when we have following time duration except:a.Optimistic timeb.Pessimistic timec.Most likely timed.Certain Duration