There’s a problem! The Scrum master, product owner and development team all have different estimations when planning how long a sprint will take. One thinks 8 days, one thinks 12 days, and the other thinks 10 days. Then, they consult with a subject matter expert who estimates 14 days. When planning, whose estimate should be used?Question 2Select one:a.Scrum masterb.Subject matter expertc.Product ownerd.Development team
Question
There’s a problem! The Scrum master, product owner and development team all have different estimations when planning how long a sprint will take. One thinks 8 days, one thinks 12 days, and the other thinks 10 days. Then, they consult with a subject matter expert who estimates 14 days. When planning, whose estimate should be used?Question 2Select one:a.Scrum masterb.Subject matter expertc.Product ownerd.Development team
Solution
In Scrum, it's the development team that is responsible for estimating the work. This is because they are the ones who will be doing the work and have the best understanding of what it will entail. Therefore, the estimate of the development team should be used. So, the answer is d. Development team.
Similar Questions
Scrum Estimates
As a project manager, you try to get an accurate time estimate for a task by communicating with an expert. After receiving their time estimate, you ask questions like, “What equipment do you suppose you’ll have?” and “How many people do you expect to work on the task?” What strategy for getting an accurate time estimate did you choose?1 pointAssess the expert’s confidence level in their estimate.Ask the expert how likely it is that assumptions they have might not work out and how it would affect their estimate.Discuss the assumptions the expert may be making when they give an estimate.Check the expert’s estimates against the actual time spent on similar tasks in previous work.4.Question 4
As a project manager, you identify tasks to complete in a project. Who will you consult to create an accurate time estimate for each task?1 pointA project manager from a different teamThe sponsors of the projectTeam members working on the tasksThe project’s primary stakeholders
Question 4Select the correct statement regarding sprint planning.1 pointThe scrum master describes the goal.The product owner creates new milestones and gives them titles.The development team takes the stories from the top of the product backlog and assigns them to the sprint backlog.The product owner determines the team velocity.
Question 6In Scrum, who determines priorities and how work is accomplished?1 pointThe scrum team negotiates commitments with the product owner and has authority on how to reach commitments.The scrum master reprioritizes the backlog and directs the team.The customer determines priorities and how the work is carried out.The project owner directs how and when work will be done, and which team members will do it.