The ________ indexes compare the to-date progress to the end of the project.Multiple choice question.percent completecost performanceschedule performance
Question
The ________ indexes compare the to-date progress to the end of the project.Multiple choice question.percent completecost performanceschedule performance
Solution
The correct answer is "schedule performance". This index compares the work performed to date with the work planned for the same period. If the schedule performance index (SPI) is greater than one, it means the project is ahead of schedule. If it's less than one, the project is behind schedule.
Similar Questions
The percent complete index actual costs assumes the ____________ is (are) the most reliable information for measuring percent complete.Multiple choice question.schedule performance index and cost performance indexactual costs-to-date and expected cost at completionoriginal budget of work completepercent complete rule
Periodic monitoring and measuring of the status of the project allow for comparisons of _________.Multiple choice question.actual versus expected plansdata from past projects to current performancemanagement targets and market performance
Discuss various performance indices.
Measuring progress and performance is the _______ step in creating a project control system for measuring and evaluating project performance.Multiple choice question.thirdfirstsecondlast
Multiple Choice QuestionThe third step in the project control process of the measurement and evaluation of project performance is ___.Multiple choice question.measure both progress and performancecomparing planned against actual performancereview the baseline plan with top managementanalyze inputs to the control system
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.