Slack= latest finish time minus?a.Earliest finish timeb.Newest finish timec.Average finish timed.Project duration
Question
Slack= latest finish time minus?a.Earliest finish timeb.Newest finish timec.Average finish timed.Project duration
Solution
To calculate the slack, you need to subtract the earliest finish time from the latest finish time.
Similar Questions
Represents the amount of time an activity can be delayed without impacting the critical path or project completion.a.Slackb.Nodesc.Activitiesd.Duration
Which of the following represent individual tasks or activities in the project.a.Slackb.Nodesc.Critical Pathd.Duration
In a CPM analysis, the activity's slack time can be determined by subtracting the early start from the early finish.Group of answer choicesTrueFalse
The latest possible time an activity can start without delaying the projecta.Latest start timeb.Latest finish timec.Project Costd.Duration
The earliest finish time for an activity is equal to the latest finish time minus the activity slack.Group startsTrue or False