Knowee
Questions
Features
Study Tools

Fletcher Company collected the following data regarding production of one of its products. Compute the total direct labor variance. Direct labor standard (2 hours @ $12.75/hour) $ 25.50 per finished unitActual direct labor hours 81,500 hoursActual finished units produced 40,000 unitsActual cost of direct labor $ 1,100,250  Multiple Choice$80,250 favorable.$61,125 favorable.$80,250 unfavorable.$61,125 unfavorable.$19,125 favorable.

Question

Fletcher Company collected the following data regarding production of one of its products. Compute the total direct labor variance. Direct labor standard (2 hours @ 12.75/hour)12.75/hour) 25.50 per finished unitActual direct labor hours 81,500 hoursActual finished units produced 40,000 unitsActual cost of direct labor 1,100,250 MultipleChoice 1,100,250  Multiple Choice80,250 favorable.61,125favorable.61,125 favorable.80,250 unfavorable.61,125unfavorable.61,125 unfavorable.19,125 favorable.

...expand
🧐 Not the exact question you are looking for?Go ask a question

Solution

To calculate the total direct labor variance, we need to compare the actual cost of direct labor to the standard cost of direct labor.

Step 1: Calculate the Standard Cost of Direct Labor The standard cost is the amount that the labor should have cost to produce the finished units. This is calculated by multiplying the standard labor hours per unit by the standard labor cost per hour, and then multiplying by the number of units produced.

Standard labor hours per unit = 2 hours Standard labor cost per hour = $12.75 Number of units produced = 40,000 units

Standard cost = (2 hours/unit * 12.75/hour40,000units)=12.75/hour * 40,000 units) = 1,020,000

Step 2: Calculate the Actual Cost of Direct Labor The actual cost is given as $1,100,250.

Step 3: Calculate the Total Direct Labor Variance The total direct labor variance is the actual cost minus the standard cost.

Total direct labor variance = Actual cost - Standard cost Total direct labor variance = 1,100,2501,100,250 - 1,020,000 = $80,250

Because the actual cost is higher than the standard cost, this is an unfavorable variance. So, the answer is $80,250 unfavorable.

This problem has been solved

Similar Questions

Fletcher Company collected the following data regarding production of one of its products. Compute the standard quantity allowed for the actual output. Direct materials standard (6 pounds @ $2/pound) $ 12 per finished unitActual direct materials used 251,000 poundsActual finished units produced 31,000 unitsActual cost of direct materials used $ 251,000

Given the following information, calculate the direct labor price variance.  Actual production in units17,000Standard labor cost per unit1/2 hour @ $20 per hourActual cost for labor$216,750 for 12,750 hoursMultiple choice question.$72,750 unfavorable$38,250 unfavorable$72,750 favorable$38,250 favorable

Multiple Choice QuestionABC Company has set the following standards for one unit of product: Direct materials: 0.5 pounds @ $1.00 per pound; Direct labor: 1 hour @ $10.00 per hour. The company produced 35,000 units and had the following actual costs: Direct materials: 18,000 pounds at a total cost of $17,280; Direct labor: 36,000 hours at a total cost of $374,400. Compute the direct labor variance.Multiple choice question.$14,400 F$14,400 U$24,400 U$24,400 F

Use the following data to find the direct labor rate variance if the company produced 3,500 units during the period. Direct labor standard (4 hours @ $12/hour) $ 48 per unitActual hours worked 12,250  Actual rate per hour $ 12.50  Multiple Choice$21,000 favorable.$6,125 unfavorable.$7,000 unfavorable.$14,875 favorable.$7,000 favorable.

ABC Company has set the following standards for one unit of product: Direct materials: 0.5 pounds @ $1.00 per pound; Direct labor: 1 hour @ $10.00 per hour. The company produced 35,000 units and had the following actual costs: Direct materials: 18,000 pounds at a total cost of $17,280; Direct labor: 36,000 hours at a total cost of $374,400. Compute the direct labor rate variance.Multiple choice question.$14,400 U$10,000 F$10,000 U$14,400 F

1/2

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.