Given the following information, calculate the direct labor price variance. Actual production in units17,000Standard labor cost per unit1/2 hour @ $20 per hourActual cost for labor$216,750 for 12,750 hoursMultiple choice question.$72,750 unfavorable$38,250 unfavorable$72,750 favorable$38,250 favorable
Question
Given the following information, calculate the direct labor price variance. Actual production in units17,000Standard labor cost per unit1/2 hour @ 216,750 for 12,750 hoursMultiple choice question.38,250 unfavorable38,250 favorable
Solution
To calculate the direct labor price variance, we need to follow these steps:
-
Calculate the Standard Cost per Hour: The standard labor cost per unit is 1/2 hour at 20.
-
Calculate the Actual Cost per Hour: The actual cost for labor is 216,750 / 12,750 hours = $17 per hour.
-
Calculate the Direct Labor Price Variance: The formula for the direct labor price variance is (Standard Cost per Hour - Actual Cost per Hour) * Actual Hours. So, the direct labor price variance is (17) * 12,750 hours = $38,250.
-
Determine if the Variance is Favorable or Unfavorable: If the actual cost per hour is less than the standard cost per hour, the variance is favorable. If the actual cost per hour is more than the standard cost per hour, the variance is unfavorable. In this case, the actual cost per hour is less than the standard cost per hour, so the variance is favorable.
So, the answer is $38,250 favorable.
Similar Questions
Use the following data to find the direct labor rate variance if the company produced 3,500 units during the period. Direct labor standard (4 hours @ $12/hour) $ 48 per unitActual hours worked 12,250 Actual rate per hour $ 12.50 Multiple Choice$21,000 favorable.$6,125 unfavorable.$7,000 unfavorable.$14,875 favorable.$7,000 favorable.
Multiple Choice QuestionABC Company has set the following standards for one unit of product: Direct materials: 0.5 pounds @ $1.00 per pound; Direct labor: 1 hour @ $10.00 per hour. The company produced 35,000 units and had the following actual costs: Direct materials: 18,000 pounds at a total cost of $17,280; Direct labor: 36,000 hours at a total cost of $374,400. Compute the direct labor variance.Multiple choice question.$14,400 F$14,400 U$24,400 U$24,400 F
A job was budgeted to require 2 hours of labor per unit at $11.00 per hour. The job consisted of 8,500 units and was completed in 16,000 hours at a total labor cost of $189,100. What is the total direct labor variance?
XYZ Company makes one product and has calculated the following amounts for direct labor: AH x AR = $84,000; AH x SR = $83,000; SH x SR = $85,000. Compute the direct labor cost variance.Multiple choice question.$2,000 F$1,000 U$2,000 U$1,000 F
Given the following information, calculate the direct material efficiency variance. Actual production in units17,000Standard cost for materials per unit$0.75 per pound × 3 poundsActual cost for materials$36,750 for 52,500 pounds Multiple choice question.$1,050 favorable$1,125 unfavorable$1,125 favorable$1,050 unfavorable