CPM help in Early identification of ________ activitiesa.Criticalb.Non- Criticalc.Regulard.Non- Regular
Question
CPM help in Early identification of ________ activitiesa.Criticalb.Non- Criticalc.Regulard.Non- Regular
Solution
CPM (Critical Path Method) helps in the early identification of Critical activities. So, the answer is a. Critical. This method is used in project management to identify all tasks necessary to complete a project, the time it will take to complete each task, and the relationships between the tasks. The "critical" activities are the tasks that must be completed on time in order for the project to meet its deadline.
Similar Questions
What is a particular task/exercise in a project known as CPM?a.Activityb.Eventc.Taild.Head
In a CPM analysis, the activity's slack time can be determined by subtracting the early start from the early finish.Group of answer choicesTrueFalse
Write an activity that can apply to minimize the critical path of a proj ect
A sequence of complex, connected activities that have a common goal or purposes is known as a ___________?
For an activity in a CPM analysis, the early finish time is 12 and the late finish time is 12. Which of the following statements is true? Group of answer choicesThe duration of this activity is 12.The late start is 12.The early start is 12.The activity could be on the critical path.The slack for this activity is 12.
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.