A specification was changed early in your project, causing you to overspend a bit in the first half. Your boss wants to know what the forecast costs will be at its completion. How should you proceed?Select an answer:Assume the project will underspend and be late in the second half.Assume the project will have the same amount of overspending and lateness in the second half.The overall costs will be increased unless the specification is reduced in another part of the project.Assume the project will be over budget and deliver early.
Question
A specification was changed early in your project, causing you to overspend a bit in the first half. Your boss wants to know what the forecast costs will be at its completion. How should you proceed?Select an answer:Assume the project will underspend and be late in the second half.Assume the project will have the same amount of overspending and lateness in the second half.The overall costs will be increased unless the specification is reduced in another part of the project.Assume the project will be over budget and deliver early.
Solution
The best way to proceed in this situation would be to assume the project will have the same amount of overspending and lateness in the second half. This is based on the concept of Earned Value Management (EVM), which is a project management technique for measuring project performance and progress in an objective manner.
Here are the steps you should follow:
-
Calculate the Cost Performance Index (CPI): This is the ratio of earned value (EV) to actual cost (AC). If the CPI is less than 1, it means the project is over budget.
-
Calculate the Estimate at Completion (EAC): This is a forecast of what the total project cost will be at the end of the project. It can be calculated using the formula EAC = BAC / CPI, where BAC is the Budget at Completion.
-
Communicate the EAC to your boss: This will give your boss an idea of what the forecast costs will be at the completion of the project.
-
Develop a plan to manage the overspending: This could involve reducing costs in other areas of the project, increasing the project budget, or negotiating changes to the project scope.
Remember, it's important to communicate openly and honestly with your boss about the situation and your plan to address it.
Similar Questions
The first half of your project ran into a problem that put the project both behind schedule and over budget. Which assumption can let you forecast that the second half will put you back on track?Select an answer:The problem will be accepted by the customer in the contract with you.The problem was inherent in the project process.The problem you encountered was a one-off.The problem you encountered was ongoing.
The process of forecasting or approximating the time and cost of completing project deliverables is called
Your boss wants to know how long your project is going to take. Which part of the plan should you share with your boss?Select an answer:the noncritical tasksthe estimated durations of all tasksthe critical paththe total amount of float in the project
A project manager predicts the cost of a project for the upcoming quarter. What is this prediction known as? 1 pointPlanned ExpenseMaterial ExpenseScheduleForecast
Which method used to revise estimates of future project costs allows experts in the field to change original baseline durations and costs because new information tells them the original estimates are not accurate?Multiple choice question.EACfEACreTCPI
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.