Which project planning document organizes the work along a visual timeline so the PM can develop a project schedule?Risk management planProject charterGantt chartWork breakdown structure (WBS)

Question

Which project planning document organizes the work along a visual timeline so the PM can develop a project schedule?Risk management planProject charterGantt chartWork breakdown structure (WBS)

🧐 Not the exact question you are looking for?Go ask a question

Solution

The project planning document that organizes the work along a visual timeline so the PM can develop a project schedule is the Gantt chart.

Similar Questions

Which project planning document is a hierarchical grouping of all activities to help the PM define scope and identify the work to estimate, assign, and track?Risk management planCommunications management planWork breakdown structure (WBS)Project charter

Which project planning document does the PM use to define how information will be shared, who it will be shared with, when it will be shared, and the format?Risk management planProject charterCommunications management planWork breakdown structure (WBS)

Project Management:                                is a visual representation of the project schedule, showing the duration of each activity and the relationship between activities.

Project planning is part of project management, which relates to the use of schedules such as Gantt chartsQuestion 5Answera.Gantt cubesb.Gantt chartsc.Gantt planesd.Gantt circles

As a project manager, you create a project plan. In the plan are documents that help keep a project organized and on track, particularly if a risk arises or a change occurs. In which section of the project plan are these documents linked? 1 pointBudgetProject scope and goalsManagement plansWork breakdown structure (WBS)

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.