Which project planning document does the PM use to define how information will be shared, who it will be shared with, when it will be shared, and the format?Risk management planProject charterCommunications management planWork breakdown structure (WBS)

Question

Which project planning document does the PM use to define how information will be shared, who it will be shared with, when it will be shared, and the format?Risk management planProject charterCommunications management planWork breakdown structure (WBS)

🧐 Not the exact question you are looking for?Go ask a question

Solution

The project planning document that the PM uses to define how information will be shared, who it will be shared with, when it will be shared, and the format is the Communications Management Plan.

Similar Questions

Which project planning document is a hierarchical grouping of all activities to help the PM define scope and identify the work to estimate, assign, and track?Risk management planCommunications management planWork breakdown structure (WBS)Project charter

Which project planning document organizes the work along a visual timeline so the PM can develop a project schedule?Risk management planProject charterGantt chartWork breakdown structure (WBS)

Which of the following is a document that provides guidance on how a project is executed and controlled to ensure successful delivery of the project goals?Work breakdown structureProject planResource planRisk management plan

As a project manager, you create a project plan. In the plan are documents that help keep a project organized and on track, particularly if a risk arises or a change occurs. In which section of the project plan are these documents linked? 1 pointBudgetProject scope and goalsManagement plansWork breakdown structure (WBS)

As a project manager, you create a project plan. In the plan are tasks with clear descriptions, owners, and due dates. In which section of the project plan do these tasks reside?1 pointScope and goalsBudgetWork breakdown structure (WBS)Management plans