Which of the following is a true statement regarding the schedule management plan? A. It may or may not be written depending on the project management approach of the company executives B. It can be formal or informal, highly detailed or broad in nature depending on the project, and it is a key input to the Define Activities process C. It must be formal and highly detailed prior to project management plan approval D. It requires the input of all stakeholders involved in the project and those that will eventually approve the plan
Question
Which of the following is a true statement regarding the schedule management plan? A. It may or may not be written depending on the project management approach of the company executives B. It can be formal or informal, highly detailed or broad in nature depending on the project, and it is a key input to the Define Activities process C. It must be formal and highly detailed prior to project management plan approval D. It requires the input of all stakeholders involved in the project and those that will eventually approve the plan
Solution
The correct statement regarding the schedule management plan is B. "It can be formal or informal, highly detailed or broad in nature depending on the project, and it is a key input to the Define Activities process".
This is because the schedule management plan is a component of the project management plan and it establishes the criteria and the activities for developing, monitoring, and controlling the schedule. The level of detail and formality of the plan can vary based on the needs of the project. It is indeed a key input to the Define Activities process as it provides guidance on how the project schedule will be managed throughout the project.
The other options are not entirely correct. While the schedule management plan may require input from stakeholders (option D), it does not necessarily require the input of all stakeholders. It also does not have to be formal and highly detailed prior to project management plan approval (option C). The level of formality and detail is dependent on the nature of the project. Lastly, the creation of the schedule management plan is not dependent on the project management approach of the company executives (option A). It is a necessary part of the project management plan regardless of the approach taken.
Similar Questions
Which process in project schedule management involves identifying the specific tasks that the project team members and stakeholders must perform to produce the project deliverables?Group of answer choicesestimating activity durationssequencing activitiesdefining activitiesdeveloping the schedule
After working with key stakeholders to define activities and calculate their resources, what is the next process in project schedule management?Group of answer choicesdetermine their dependenciesdevelop the schedule.estimate the duration of activitiescontrol the schedule.
In project schedule management, the main goal of which process is to ensure that the project team has complete understanding of all the work they must do as part of the project scope so they can start scheduling the work?Group of answer choicesestimating activity durationsestimating activity resourcesdefining activitiescontrolling the schedule
In the process of project planning, which of the following statements is true? All project plans must be completed in a defined sequence.If any one part of the project plan changes, the remaining parts of the plan should not be altered.The desirable planning sequence depends on the project.Different parts of the project plan will have no impact on the performance of the others.
Which of the following provides a sequenced plan that estimates the time required to complete project activities and tasks?Project planProject scheduleCommunication planResource plan