You are the project manager on a software development project. A scope change request has been approved. This should be reflected in:2 MarksScope Management PlanProject Management PlanChange Management PlanConfiguration Management Plan

Question

You are the project manager on a software development project. A scope change request has been approved. This should be reflected in:2 MarksScope Management PlanProject Management PlanChange Management PlanConfiguration Management Plan

🧐 Not the exact question you are looking for?Go ask a question

Solution

The approved scope change request should be reflected in the Project Management Plan. This plan is a formal, approved document that defines how the project is executed, monitored, and controlled. It includes all subsidiary plans including the scope management plan and the change management plan. Therefore, any approved changes in the project, including scope changes, should be updated in the Project Management Plan.

This problem has been solved

Similar Questions

Which of the following statements best describes the project manager's responsibilities in relation to scope change managementGroup of answer choicesThe project manager is responsible for relaying all change requests to a change control board and informing the customer about the board's decisions.The project manager is responsible for making all final decisions about the disposition of change requests and communicating those decisions to project stakeholders.The project manager is responsible for making sure all the client's change requests are carried out promptly.The project manager is responsible for identifying and documenting potential changes, assessing their impact on the project, providing that assessment to the change control board, documenting the decisions, and communicating them to project stakeholders.

A change of government in one of the countries would require changes to the stakeholder register, and risk register, but not the scope. A change request would need to be submitted under the Perform Integrated Change Control process to manage the scope. Group of answer choicesTrueFalse

As a project manager, you need to update your project charter with a statement about the tangible outcome of the project. Which section of the project charter does this belong to?1 pointProject deliverableBusiness caseProject scopeBenefits

A major characteristic of scope validation is:Group of answer choicesCustomer/client acceptance of project deliverablesImproved cost estimatesImproved schedule estimatesAn improved project management information system

Which of the following does a project manager do after a change request is approved? Updates the communication planImplements a contingency planRe-baselines the budget and scheduleCreates an impact statement