Question 4As a project manager, you have a weekly video conference with stakeholders as part of your communication plan. What additional details should the communication plan include? Select all that apply.1 pointGoalLocationKey datesDuration
Question
Question 4As a project manager, you have a weekly video conference with stakeholders as part of your communication plan. What additional details should the communication plan include? Select all that apply.1 pointGoalLocationKey datesDuration
Solution
The communication plan should include all of the following details:
-
Goal: The purpose of the communication or what you hope to achieve. This could be updating stakeholders on progress, discussing issues, or making decisions.
-
Location: Where the communication will take place. In this case, it's a video conference, so the location could be the platform or software you're using (like Zoom or Skype).
-
Key Dates: When the communication will happen. This could be the date and time of the video conference.
-
Duration: How long the communication is expected to last. For a meeting, this would be the start and end time.
So, all the options apply.
Similar Questions
Which of the following are included in the project plan? Select all that apply.1 pointTasksRetrospectivesPeopleTime
As a project manager, part of your communication plan is to identify risks and present barriers in-person. What additional details should the communication plan include? Select all that apply.1 pointDurationLocationFrequencyType of communication
Question 7What is the typical communication plan for key stakeholders in a project?1 pointBacklog discussion sessions to review tasksLaunch prep schedule every six weeksMonthly emails with a status update overviewDaily check-ins scheduled with task updates
Fill in the blank: Project managers should identify project stakeholders, communication methods, communication goals, and communication _____ before creating a communication plan. 1 pointfrequencyrisksconsequences costs
Imagine that a restaurant is hosting a recruitment day to hire delivery drivers. The project manager creates a plan to organize stakeholder communication. The plan indicates the following:The team lead updates the core hiring team every day for two weeks prior to the event to report next steps so they each know their daily responsibilities.The core hiring team contacts the job candidates the Friday before the event to remind them of the time and location.The project manager contacts the venue and caterers the Monday before the event to confirm reservations. In the above scenario, what three key elements are missing from the communication plan?1 pointType of communicationResource linksCommunication risksDependenciesDelivery methods
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.