15 men can type 3000 pages in 6 days working 2 hours per day. How many men would be required to type 3600 pages working 4 hours per day for 3 days?Options10122518
Question
15 men can type 3000 pages in 6 days working 2 hours per day. How many men would be required to type 3600 pages working 4 hours per day for 3 days?Options10122518
Solution
To solve this problem, we first need to find out how many pages one man can type in one hour.
From the given problem, we know that 15 men can type 3000 pages in 6 days working 2 hours per day.
So, total hours worked by 15 men = 6 days * 2 hours/day = 12 hours
Therefore, the number of pages typed by one man in one hour = 3000 pages / (15 men * 12 hours) = 16.67 pages/hour
Next, we need to find out how many men would be required to type 3600 pages working 4 hours per day for 3 days.
Total hours available for the new task = 3 days * 4 hours/day = 12 hours
Therefore, the number of men required = 3600 pages / (16.67 pages/hour * 12 hours) = 18 men
So, 18 men would be required to type 3600 pages working 4 hours per day for 3 days.
Similar Questions
Select the correct answerP, Q and R are three typists who working simultaneously can type 216 pages in 4 hours. In one hour, R can type as many pages more than Q as Q can type more than P. During a period of five hours. R can type as many pages as P can during seven hours. How many pages does each of them type per hour?Options15, 17, 2214, 17, 2015, 18, 2116, 18, 22
Select the correct answerIf 36 men can do a piece of work in 25 hours, in how many hours will 15 men do it?Options36 hours72 hours60 hours40 hours
Ty has 230 pages of text to read in the next three days. If he averages 25 pages every 1 14 hours, how many hours is he going to be spending reading this text?
Select the correct answer6 men finish one-forth work in 2 days. The number of additional men required for finishing the same work in 2 days is?Options18 men28 men14 men24 men
Question No. 15DIRECTIONS for question 15: Type in your answer in the input box provided below the question.Three men and four women working together can do a piece of work in four days, whereas four men and two women working together require six days to complete the same work. In how many days can nine men and two women working together finish the work?
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.