Multiple Choice Question Estimated manufacturing overhead$500,000Estimated direct labor cost$250,000Actual manufacturing overhead$720,000Actual direct labor cost$300,000 Based on this information, the predetermined overhead rate per direct labor dollar is:Multiple choice question.$2.88$2.00$1.67 $2.40

Question

Multiple Choice Question Estimated manufacturing overhead500,000Estimateddirectlaborcost500,000Estimated direct labor cost250,000Actual manufacturing overhead720,000Actualdirectlaborcost720,000Actual direct labor cost300,000 Based on this information, the predetermined overhead rate per direct labor dollar is:Multiple choice question.2.882.882.001.67 1.67 2.40

🧐 Not the exact question you are looking for?Go ask a question

Solution

The predetermined overhead rate is calculated by dividing the estimated manufacturing overhead by the estimated direct labor cost.

Here's the step-by-step calculation:

  1. Identify the estimated manufacturing overhead. From the question, we know that it is $500,000.

  2. Identify the estimated direct labor cost. From the question, we know that it is $250,000.

  3. Divide the estimated manufacturing overhead by the estimated direct labor cost.

    So, 500,000/500,000 / 250,000 = $2.00

Therefore, the predetermined overhead rate per direct labor dollar is $2.00.

This problem has been solved

Similar Questions

Estimated manufacturing overhead$450,000Estimated direct labor hours150,000Actual manufacturing overhead$405,000Actual direct labor hours180,000 Based on this information, the predetermined overhead rate per direct labor hour is $. (Enter your answer as a whole number.)

Use the following information to answer the next question:Estimated manufacturing overhead$520,000Estimated machine hours16,000Actual machine hours worked15,000Actual overhead costs incurred:  Indirect materials$180,000  Indirect labour$135,000  Utilities$ 40,000  Insurance$ 20,000  Rent$150,000If the company uses a predetermined overhead rate to apply overhead, manufacturing overhead applied would be:Question 2Select one:a.$487,500b.$520,000c.$525,000d.$554,667

A company works on three jobs and incurs the following: Direct materials - $50,000 and Direct labor - $100,000. The company uses a predetermined overhead rate of 60% of direct labor costs. How much overhead will be allocated to the three jobs?Multiple choice question.$60,000$50,000$15,000$75,000

At the beginning of the year, Custom Manufacturing set its predetermined overhead rate using the following estimates: overhead costs, $1,240,000, and direct materials costs, $400,000.At year-end, the company reports that actual overhead costs for the year are $1,249,900 and actual direct materials costs for the year are $400,000.Determine the predetermined overhead rate using estimated direct materials costsEnter the actual overhead costs incurred and the amount of overhead cost applied to jobs during the year using the predetermined overhead rate. Determine whether overhead is over- or underapplied (and the amount) for the year.Prepare the entry to close any over- or underapplied overhead to Cost of Goods Sold.

Multiple Choice QuestionLanden Company uses a single plantwide overhead rate based on direct labor hours. Total budgeted overhead costs are $200,000. Total budgeted direct materials are $50,000 and total budgeted direct labor hours are 80,000. What is the plantwide overhead rate per direct labor hour?Multiple choice question.$2.50$4.00$0.40$0.25