The project manager has identified the goals, barriers, and communication methods for a project. What is the final piece they must determine before creating the communication plan?1 pointStakeholder analysisTeam feedbackTeam membersKey stakeholders

Question

The project manager has identified the goals, barriers, and communication methods for a project. What is the final piece they must determine before creating the communication plan?1 pointStakeholder analysisTeam feedbackTeam membersKey stakeholders

🧐 Not the exact question you are looking for?Go ask a question

Solution

The final piece the project manager must determine before creating the communication plan is the "Key stakeholders". This is because the key stakeholders are the ones who will be directly affected by the project's outcome. They are the ones who need to be communicated with effectively and efficiently to ensure the project's success.

Similar Questions

Fill in the blank: Project managers should identify project stakeholders, communication methods, communication goals, and communication _____ before creating a communication plan. 1 pointfrequencyrisksconsequences costs

As a project manager, part of your communication plan is to identify risks and present barriers in-person. What additional details should the communication plan include? Select all that apply.1 pointDurationLocationFrequencyType of communication

Question 7What is the typical communication plan for key stakeholders in a project?1 pointBacklog discussion sessions to review tasksLaunch prep schedule every six weeksMonthly emails with a status update overviewDaily check-ins scheduled with task updates

What is the purpose of a communication plan? 1 pointCentralize project documentation Organize and document the processes, types, and expectations of communicationEstablish roles and responsibilities for team members Outline a process for knowledge management

An effective project management communication plan can help with which of the following processes? Select all that apply. 1 pointCulture developmentChange managementProject continuityTeam selection