What are three major project components that are worked out during the planning phase?1 pointSuccess criteria, stakeholders, and resourcesSchedule, budget, and risk management planScope, goals, and deliverablesProject tracking, quality management, and retrospectives
Question
What are three major project components that are worked out during the planning phase?1 pointSuccess criteria, stakeholders, and resourcesSchedule, budget, and risk management planScope, goals, and deliverablesProject tracking, quality management, and retrospectives
Solution
The three major project components that are worked out during the planning phase are:
-
Scope: This refers to what the project is expected to achieve, including the specific tasks and activities that need to be completed to deliver the project.
-
Goals: These are the specific objectives that the project is designed to achieve. They should be clear, measurable, and defined at the beginning of the project.
-
Deliverables: These are the tangible or intangible goods or services that will be delivered to the client or stakeholder at the end of the project.
These components are crucial as they provide a clear direction and framework for the project, ensuring that everyone involved understands what needs to be done, when it needs to be done, and what the final outcome should be.
Similar Questions
As a project manager in the planning phase, you have created a project schedule and accounted for the total costs. What is the third major planning component you will create?1 pointA team performance chartA work breakdown structureA risk management planA feedback form
Which of the following components of a project plan is completed first? Work breakdown structureRisk management planProject budgetProject schedule
What are the basic elements that make up a project plan?1 pointTime estimation, effort estimation, buffer, and sub-tasksTasks, milestones, people, documentation, and timeInitiation, planning, managing, and executionStakeholder information, project proposal, tools, and resources
You have gathered information from project documentation and the project team. With this information, you identified and created a list of tasks for your project plan. What is the next step for completing your project plan?1 pointIdentify tasks that carry a high risk.Identify tasks that stakeholders have a particular interest in.Identify the order in which tasks need to be completed. Identify points in the project plan where you can evaluate completed work.
Which of the following activities is NOT usually a part of Phase 3 of the project?a.)Managing the overall team performanceb.)Developing the project budgetc.)Managing risks and any changes to the projectd.)Monitoring the work completion