Which among the following is a key consideration made by the Agile Framework? (Check all that apply)Tools and ProcessesCustomer CollaborationFollowing a defined planResponding to change

Question

Which among the following is a key consideration made by the Agile Framework? (Check all that apply)Tools and ProcessesCustomer CollaborationFollowing a defined planResponding to change

🧐 Not the exact question you are looking for?Go ask a question

Solution

The Agile Framework primarily considers the following:

  1. Customer Collaboration: Agile methodology emphasizes customer satisfaction and values customer collaboration over contract negotiation. It involves the customer throughout the development process to get regular feedback and ensure the product meets their needs.

  2. Responding to Change: Agile is all about flexibility and adaptability. It values responding to change over following a fixed plan. Agile teams are ready to adapt to changes at any stage of the project to provide the best possible outcome.

While tools and processes are important, they are not the key consideration in Agile. The same goes for following a defined plan. Agile values individuals and interactions, and responding to change more.

This problem has been solved

Similar Questions

Which among the following is a key consideration made by the Agile Framework? (Check all that apply)Following a defined planTools and ProcessesCustomer CollaborationResponding to change

Which among the following is a key consideration made by the Agile Framework? (Check all that apply)

Question 1Which of the following is not an emphasis of an Agile development process?1 pointindividuals and interactionscomprehensive test planclient involvement/collaborationworking softwareresponsiveness to change

Which set of priorities is the opposite of the ideals put forth in the Agile Manifesto? Processes and tools above individuals and interactionsWorking software over comprehensive documentationCustomer collaboration over contract negotiationResponding to change over following a plan

Which of the following is NOT one of the 4 Agile Values?Customer collaborationPlanning and meetingWorking SoftwareIndividuals and interactions