Knowee
Questions
Features
Study Tools

ABC Company's production budget for April included the following for raw materials: Budgeted production = 35,000 units; Budgeted raw materials unit cost = $16 per unit. ABC Company's actual production for April was the following: Actual production = 36,000 units; Actual raw materials cost = $16.20 per unit.Calculate the following items for ABC's April performance report for raw materials:Original budget = $.Flexed budget = $.Actual cost = $.Variance = $.Use F or U to identify the variance as Favorable or Unfavorable.

Question

ABC Company's production budget for April included the following for raw materials: Budgeted production = 35,000 units; Budgeted raw materials unit cost = 16perunit.ABCCompanysactualproductionforAprilwasthefollowing:Actualproduction=36,000units;Actualrawmaterialscost=16 per unit. ABC Company's actual production for April was the following: Actual production = 36,000 units; Actual raw materials cost = 16.20 per unit.Calculate the following items for ABC's April performance report for raw materials:Original budget = .Flexedbudget=.Flexed budget = .Actual cost = .Variance=.Variance = .Use F or U to identify the variance as Favorable or Unfavorable.

...expand
🧐 Not the exact question you are looking for?Go ask a question

Solution 1

To calculate the values for ABC's April performance report for raw materials, follow these steps:

  1. Original Budget: This is calculated by multiplying the budgeted production units by the budgeted raw materials unit cost. So, 35,000 units * 16/unit=16/unit = 560,000.

  2. Flexed Budget: This is calculated by multiplying the actual production units by the budgeted raw materials unit cost. So, 36,000 units * 16/unit=16/unit = 576,000.

  3. Actual Cost: This is calculated by multiplying the actual production units by the actual raw materials unit cost. So, 36,000 units * 16.20/unit=16.20/unit = 583,200.

  4. Variance: This is calculated by subtracting the flexed budget from the actual cost. So, 583,200583,200 - 576,000 = $7,200.

  5. Variance Identification: If the actual cost is greater than the flexed budget, the variance is unfavorable (U). If the actual cost is less than the flexed budget, the variance is favorable (F). In this case, because the actual cost (583,200)isgreaterthantheflexedbudget(583,200) is greater than the flexed budget (576,000), the variance is Unfavorable (U).

So, the answers are:

Original budget = 560,000.Flexedbudget=560,000. Flexed budget = 576,000. Actual cost = 583,200.Variance=583,200. Variance = 7,200 U.

This problem has been solved

Solution 2

To calculate the values for ABC's April performance report for raw materials, follow these steps:

  1. Original Budget: This is calculated by multiplying the budgeted production units by the budgeted raw materials unit cost. So, 35,000 units * 16/unit=16/unit = 560,000.

  2. Flexed Budget: This is calculated by multiplying the actual production units by the budgeted raw materials unit cost. So, 36,000 units * 16/unit=16/unit = 576,000.

  3. Actual Cost: This is calculated by multiplying the actual production units by the actual raw materials unit cost. So, 36,000 units * 16.20/unit=16.20/unit = 583,200.

  4. Variance: This is calculated by subtracting the flexed budget from the actual cost. So, 583,200583,200 - 576,000 = $7,200.

  5. Variance Identification: Since the actual cost is higher than the flexed budget, the variance is unfavorable. So, the variance is U.

So, the answers are:

Original budget = 560,000.Flexedbudget=560,000. Flexed budget = 576,000. Actual cost = 583,200.Variance=583,200. Variance = 7,200 U.

This problem has been solved

Similar Questions

ABC Company's performance report for April included the following for direct labor: Budgeted cost = $33,500; Actual cost = $32,200; Variance = $. Use F or U to identify the variance as favorable or unfavorable: .

ABC Company's production budget for April included the following for direct labor: Budgeted production = 15,000 units; Budgeted direct labor unit cost = $24 per unit. ABC Company's actual production for April was the following: Actual production = 16,000 units; Actual direct labor cost = $25.00 per unit.Calculate the following items for ABC's April performance report for direct labor:Original budget = $.Flexed budget = $.

ABC Company's production budget for October is based on 500 units. Standard unit cost for raw materials is $130 per unit ($10 per pound x 13 pounds per unit). ABC's actual production in October = 525 units. The actual cost of materials used = $69,300 ($11 per pound x 12 pounds per unit).Calculate the raw materials usage variance for October:Raw materials usage variance = $.Use F or U to identify the variance as Favorable or Unfavorable: .

ABC Company's performance report for April included the following for sales revenue: Budgeted revenue = $98,000; Actual revenue = $93,000; Variance = $. Use F or U to identify the variance as favorable or unfavorable: .

ABC Company has set the following standards for one unit of product: Direct materials: 0.5 pounds @ $1.00 per pound; Direct labor: 1 hour @ $10.00 per hour. The company produced 35,000 units and had the following actual costs: Direct materials: 18,000 pounds at a total cost of $17,280; Direct labor: 36,000 hours at a total cost of $374,400. Compute the direct materials variance.Multiple choice question.$220 U$720 U$220 F$720 F

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.