A Risk Profile Analysis is essential to be undertaken prior to putting a Contract together because:Group of answer choicesIt allows the drafter to allocate responsibilities/obligations onto the person who is best able to manage itIt allows the Parliament to allocate responsibilities/obligations onto the person who is best able to manage itIt is required under the Home Building Act LegislationIt allows the Contractor to allocate responsibilities/obligations onto the person who is best able to manage it

Question

A Risk Profile Analysis is essential to be undertaken prior to putting a Contract together because:Group of answer choicesIt allows the drafter to allocate responsibilities/obligations onto the person who is best able to manage itIt allows the Parliament to allocate responsibilities/obligations onto the person who is best able to manage itIt is required under the Home Building Act LegislationIt allows the Contractor to allocate responsibilities/obligations onto the person who is best able to manage it

...expand
🧐 Not the exact question you are looking for?Go ask a question

Solution

The correct answer is: It allows the drafter to allocate responsibilities/obligations onto the person who is best able to manage it.

Here's why:

  1. A Risk Profile Analysis is a process that helps identify and assess potential risks that could affect the performance of a contract.

  2. By conducting a Risk Profile Analysis before drafting a contract, the drafter can understand the potential risks involved and determine who is best equipped to manage each risk.

  3. This allows the drafter to allocate responsibilities and obligations in the contract accordingly, ensuring that each risk is managed by the most capable party.

  4. This process is not specifically related to the Parliament or the Home Building Act Legislation, nor is it solely for the benefit of the Contractor. It is a general practice that benefits all parties involved in a contract by ensuring risks are properly managed.

This problem has been solved

Similar Questions

Multiple Choice QuestionWhat term is used to describe the documents needed to develop an adequate risk response control plan?Multiple choice question.Project Scope.Work Breakdown Structure Dictionary.Work Breakdown Structure.Risk Register.

A plan that is developed for risks that have a high impact on meeting project objectives and are implemented if attempts to reduce the risk are ineffective is referred to as:Group of answer choicesManagement ReserveContingency planFallback PlanContingency Reserve

Multiple Choice QuestionWhat is required in order for risk response control to succeed?Multiple choice question.Documentation of responsibilityWork Breakdown Structure dictionaryMitigation of risk likelihood

What are the four basic components of a risk assessment in the hazard mitigation planning process?

Mention two Inputs, Tools & Techniques, and the Outputs of each of these processes involved in risk management:Identify RisksImplement Risk Responses

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.