Knowee
Questions
Features
Study Tools

A can complete a work in 12 days, B in 15 days. When A and B worked alternatively, when started byOptions12 1/4days14 1/4days12 3/4days13 1/4days

Question

A can complete a work in 12 days, B in 15 days. When A and B worked alternatively, when started byOptions12 1/4days14 1/4days12 3/4days13 1/4days

🧐 Not the exact question you are looking for?Go ask a question

Solution 1

The problem is asking how long it would take for A and B to complete a task if they worked on it alternately, starting with A.

Step 1: Determine how much work each person can do in a day.

A can complete the work in 12 days, so A can do 1/12 of the work in a day. B can complete the work in 15 days, so B can do 1/15 of the work in a day.

Step 2: Determine how much work is done in two days (one day for A and one day for B).

In two days, A and B together can do 1/12 + 1/15 = 5/60 + 4/60 = 9/60 = 3/20 of the work.

Step 3: Determine how many two-day periods are needed to complete the work.

Since 3/20 of the work is done in two days, it would take 20/3 two-day periods to complete the work. This is approximately 6.67 two-day periods.

Step 4: Calculate the total time taken.

Since each two-day period actually represents two days of work, we multiply the number of two-day periods by 2 to get the total number of days.

6.67 * 2 = 13.33 days

However, since A and B are working alternately and A starts, the last day will be a full day of work for A. Since A can do more work in a day than B, the total time taken will be slightly less than 13.33 days.

So, the closest answer is 13 1/4 days.

This problem has been solved

Solution 2

The problem seems to be about calculating the time it takes for two people, A and B, to complete a task when they work alternately. However, the question is not clearly stated. Could you please rephrase or provide more details?

Solution 3

The question seems to be asking how long it would take for A and B to complete a task if they worked on it alternately, starting with A. Here's how you can solve it:

  1. First, find out how much work A and B can do in a day. A can complete the work in 12 days, so A can do 1/12 of the work in a day. Similarly, B can do 1/15 of the work in a day.

  2. Next, find out how much work A and B can do together in two days (since they are working alternately). In two days, A and B can do (1/12 + 1/15) of the work. Simplify the fraction to get 9/60 or 3/20 of the work.

  3. To find out how long it would take for A and B to complete the work, divide the total work (1) by the amount of work they can do in two days (3/20). This gives you 20/3 or 6 2/3 sets of two days.

  4. Since each set is two days, multiply 6 2/3 by 2 to get 13 1/3 days. However, since A starts the work and they are working alternately, A will work on the 14th day.

  5. Therefore, the work will be completed in 14 1/3 days. But since we don't have that option, the closest one is 14 1/4 days.

This problem has been solved

Similar Questions

Select the correct answerA can complete a work in 12 days, B in 15 days. When A and B worked alternatively, when started byOptions13 1/4days12 1/4days14 1/4days12 3/4daysFinish ClearPrev Next (1)

A can complete a work in 12 days, B in 15 days. If A started two days later, in comparison to B.Options7 7/97 5/97 4/97 8/9

A can complete a work in 12 days, B in 15 days. Find the time taken by them. When A and B working together.Options6 2/36 1/35 2/35 1/3

A alone can complete a work in 16 days and B alone in 12 days. Starting with A, they work on alternate days. The total work will be completed in ______.A 12 days B 13 days C  days D  days

ect answerA can complete a work in 12 days, B in 15 days. Find the time taken by them: If A leaves two days before the scheduled completion of the work.Options9 1/69 5/69 4/79 2/3

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.