ABC Company's production budget for October is based on 500 units. Standard unit cost for variable overhead is $25 per unit ($5 per hour x 5 hours per unit). ABC's actual production in October = 525 units. The actual cost of variable overhead = $18,900 ($6 per hour x 6 hours per unit).Calculate the variable overhead spending variance for October:Variable overhead spending variance = $.Use F or U to identify the variance as Favorable or Unfavorable: .

Question

ABC Company's production budget for October is based on 500 units. Standard unit cost for variable overhead is 25perunit(25 per unit (5 per hour x 5 hours per unit). ABC's actual production in October = 525 units. The actual cost of variable overhead = 18,900(18,900 (6 per hour x 6 hours per unit).Calculate the variable overhead spending variance for October:Variable overhead spending variance = $.Use F or U to identify the variance as Favorable or Unfavorable: .

...expand
🧐 Not the exact question you are looking for?Go ask a question

Solution

To calculate the variable overhead spending variance, we first need to determine the actual cost per unit and the standard cost per unit.

  1. Actual cost per unit: The actual cost of variable overhead is 18,900for525units.So,theactualcostperunitis18,900 for 525 units. So, the actual cost per unit is 18,900 / 525 = $36.

  2. Standard cost per unit: The standard unit cost for variable overhead is $25 per unit.

  3. The variable overhead spending variance is then calculated as the difference between the actual cost per unit and the standard cost per unit, multiplied by the actual number of units produced.

Variable overhead spending variance = (Actual cost per unit - Standard cost per unit) x Actual number of units = (3636 - 25) x 525 = 11x525=11 x 525 = 5775

  1. If the actual cost is higher than the standard cost, the variance is unfavorable (U). If the actual cost is lower than the standard cost, the variance is favorable (F). In this case, because the actual cost per unit (36)ishigherthanthestandardcostperunit(36) is higher than the standard cost per unit (25), the variance is Unfavorable (U).

So, the variable overhead spending variance for October is $5775 Unfavorable.

This problem has been solved

Similar Questions

ABC Company's production budget for October is based on 500 units. Standard unit cost for direct labor is $100 per unit ($20 per hour x 5 hours per unit). ABC's actual production in October = 525 units. The actual cost of direct labor = $56,700 ($18 per hour x 6 hours per unit).Calculate the direct labor rate variance for October:Direct labor rate variance = $.Use F or U to identify the variance as Favorable or Unfavorable: .

ABC Company's production budget for March is 32,000 units. Budgeted fixed overhead is $64,000. ABC's standard fixed overhead application rate is $2 per machine hour and each unit is allowed a standard of 1 hour of machine time. Actual fixed overhead for March is $67,000. Actual production in March is 36,000 units.Calculate the fixed overhead volume variance for March:Fixed overhead volume variance = $.Use F or U to identify the variance as Favorable or Unfavorable: .

ABC Company's production budget for October is based on 500 units. Standard unit cost for raw materials is $130 per unit ($10 per pound x 13 pounds per unit). ABC's actual production in October = 525 units. The actual cost of materials used = $69,300 ($11 per pound x 12 pounds per unit).Calculate the raw materials usage variance for October:Raw materials usage variance = $.Use F or U to identify the variance as Favorable or Unfavorable: .

ABC Company uses a predetermined overhead rate of $10 per direct labor hour. Actual manufacturing overhead incurred during October amounted to $35,000 when ABC worked 3,200 direct labor hours. At the end of October, the Manufacturing overhead account has a balance of $ that is (underapplied/overapplied).

Our company manufactures a single product. The production budget indicates that the number of units expected to be produced are 193,000 in October, 201,500 in November, and 198,000 in December. We assign variable overhead at a rate of $0.75 per unit of production. Fixed overhead equals $150,000 per month. Compute the total budgeted overhead that would appear on the factory overhead budget for month of October.Group of answer choices$343,000.$150,000.$144,750.$301,125.$294,750.