Consider the following organisational structures and point out which one has the highest likelihood of full-time project team members.Group of answer choicesProject-orientedOrganisationalFunctionalWeak matrix

Question

Consider the following organisational structures and point out which one has the highest likelihood of full-time project team members.Group of answer choicesProject-orientedOrganisationalFunctionalWeak matrix

🧐 Not the exact question you are looking for?Go ask a question

Solution

The organizational structure that has the highest likelihood of full-time project team members is the Project-oriented structure.

Here's why:

  1. Project-oriented structure: In this structure, teams are formed based on the project requirements. The team members are dedicated full-time to the project, making it the most likely structure to have full-time project team members.

  2. Organisational structure: This is a broad term that can include various types of structures, including functional, matrix, and project-oriented. The likelihood of full-time project team members would depend on the specific type of organizational structure.

  3. Functional structure: In a functional structure, employees are grouped based on their specific skills and their similar tasks. They have a defined role in the organization and may work on different projects but not full-time.

  4. Weak matrix structure: In a weak matrix structure, the project manager doesn't have full authority over the project and the team members. The team members might be working part-time on the project and part-time in their functional roles.

So, the project-oriented structure is the one with the highest likelihood of full-time project team members.

This problem has been solved

Similar Questions

Which one of the following organisational structures utilises people from different functional areas for a series of projects?Group of answer choicesFunctional projectCross-functional flexible teamMatrix projectPure projectIntegrated task force

A team member can work on several projects is a disadvantage of functional project structure.Group of answer choicesTrueFalse

Select all that applyAs indicated by experience and research, identify the conditions under which high-performance project teams are much more likely to develop.Multiple select question.Members serve on the project from beginning to endMembers are assigned to the project full timeMembers are assigned by a manager to serve on the project teamThe organization culture fosters cooperation and trustThere are 10 or fewer members per team

Who is responsible for planning a group project?Group of answer choicesThe group leaderThe lecturerAll members of the groupThe academic advisor

The project manager has the most authority in the __________________ type of organization.a.Functionalb.Project expediterc.Projectized organizationd.Matrix

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.