A foundation concept in Project Management is the Triple-Constraint which attempts to balance:Group of answer choicesScope - Cost - ScheduleTime - Cost - ScheduleQuality - Cost - ScheduleQuality - Scope - Cost

Question

A foundation concept in Project Management is the Triple-Constraint which attempts to balance:Group of answer choicesScope - Cost - ScheduleTime - Cost - ScheduleQuality - Cost - ScheduleQuality - Scope - Cost

🧐 Not the exact question you are looking for?Go ask a question

Solution 1

The Triple Constraint in Project Management refers to the balance between:

  1. Scope: This refers to the specific goals, deliverables, and tasks that define the boundaries of the project. The scope must be clearly defined, understood, and agreed upon from the beginning of the project.

  2. Cost: This refers to the financial resources that are necessary to execute the project. It includes all the costs required to complete the project such as labor, materials, training, equipment, etc.

  3. Time (or Schedule): This refers to the timeline that the project needs to follow for completion. It includes the start and end dates, as well as the time required for each task.

So, the correct answer is Scope - Cost - Schedule.

This problem has been solved

Solution 2

The Triple Constraint in Project Management attempts to balance:

Scope - Cost - Schedule

Here's why:

  1. The Triple Constraint, also known as the Project Management Triangle, is a model that describes the constraints of project management. These constraints are Scope, Cost, and Schedule.

  2. Scope refers to the specific goals, deliverables, and tasks that define the boundaries of the project.

  3. Cost refers to the budgeted amount for the project. It includes all the monetary resources that are required to complete the project tasks.

  4. Schedule refers to the timeline in which the project tasks need to be completed. It includes the start and end dates of the project and the estimated time for each task.

  5. The Triple Constraint theory states that changes in one constraint necessitate changes in at least one of the other constraints. For example, if the scope of a project increases (more tasks are added), then either the cost will increase (more resources are needed) or the schedule will increase (more time is needed).

  6. While quality is an important aspect of project management, it is not part of the traditional Triple Constraint. However, some modern interpretations of the model include quality as a fourth constraint, creating a "Project Management Diamond".

This problem has been solved

Similar Questions

compares it against the plan to identify variances so the PM can take corrective actions to keep the project on track while considering the triple constraints: scope, time, and costs.TrueFalse

One of the reasons assumptions are identified and defined is to:Group of answer choicesmanage associated risksallocate project resourcesarticulate budgetary needsreduce time constraintsestimate project scope

Which of these is not one of the constraints of a project? Select one: a. Resources b. Budget c. Scope d. Team

In project schedule management, the main goal of which process is to ensure that the project team has complete understanding of all the work they must do as part of the project scope so they can start scheduling the work?Group of answer choicesestimating activity durationsestimating activity resourcesdefining activitiescontrolling the schedule

Project Management Triangle consist ofa.Time, money, qualityb.Quality, Cost, Deliveryc.Scope, Time, Qualityd.Cost, Scope, Time