Fill in the Blank QuestionFill in the blank question.The Factory Services Department incurs costs of $130,000 while maintaining machinery that is operated 1,000,000 machine hours. If Job 276 requires 1,500 machine hours, the amount of costs allocated to the job will be $.

Question

Fill in the Blank QuestionFill in the blank question.The Factory Services Department incurs costs of 130,000whilemaintainingmachinerythatisoperated1,000,000machinehours.IfJob276requires1,500machinehours,theamountofcostsallocatedtothejobwillbe130,000 while maintaining machinery that is operated 1,000,000 machine hours. If Job 276 requires 1,500 machine hours, the amount of costs allocated to the job will be .

🧐 Not the exact question you are looking for?Go ask a question

Solution

To find the cost allocated to Job 276, we first need to calculate the cost per machine hour.

Step 1: Calculate the cost per machine hour Cost per machine hour = Total cost / Total machine hours Cost per machine hour = 130,000/1,000,000machinehoursCostpermachinehour=130,000 / 1,000,000 machine hours Cost per machine hour = 0.13 per machine hour

Step 2: Calculate the cost allocated to Job 276 Cost allocated to Job 276 = Cost per machine hour * Machine hours for Job 276 Cost allocated to Job 276 = 0.13permachinehour1,500machinehoursCostallocatedtoJob276=0.13 per machine hour * 1,500 machine hours Cost allocated to Job 276 = 195

So, the amount of costs allocated to Job 276 will be $195.

This problem has been solved

Similar Questions

Fill in the Blank QuestionFill in the blank question.The Production Department incurs costs of $250,000 while working 12,500 direct labor hours. If Job 421 requires 25 direct labor hours to assemble, the amount of overhead allocated to the job will be $.

ill in the Blank QuestionFill in the blank question.A manufacturing company has variable overhead costs of $2.50 per unit and fixed costs of $5,000 per month. Each unit requires 4 hours of direct labor and the company expects to produce 2,000 units each month. The standard overhead rate will be $ per direct labor hour.

A manufacturing company has the following budgeted overhead costs: Indirect materials: $0.50 per unit; Utilities: $0.25 per unit; Supervisory salaries: $60,000; Building rent: $80,000. If the company expects to produce 200,000 units using 100,000 hours of direct labor, the standard overhead rate will be $ per direct labor hour.

Job 910 was recently completed. The following data have been recorded on its job cost sheet:Direct materials $ 2,429  Direct labor-hours 74 labor-hoursDirect labor wage rate $ 17 per labor-hourMachine-hours 135 machine-hoursThe Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $18 per machine-hour. The total cost that would be recorded on the job cost sheet for Job 910 would be:Multiple Choice$6,957$3,441$3,687$6,117

Use the following information to answer the next question:Estimated manufacturing overhead$520,000Estimated machine hours16,000Actual machine hours worked15,000Actual overhead costs incurred:  Indirect materials$180,000  Indirect labour$135,000  Utilities$ 40,000  Insurance$ 20,000  Rent$150,000If the company uses a predetermined overhead rate to apply overhead, manufacturing overhead applied would be:Question 2Select one:a.$487,500b.$520,000c.$525,000d.$554,667

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.