To assist in budget control, it is suggested that the estimate occur at the _____ ____ ______ level of the WBS1. Highest2. Lowest3. Major work effort4. Third
Question
To assist in budget control, it is suggested that the estimate occur at the _____ ____ ______ level of the WBS1. Highest2. Lowest3. Major work effort4. Third
Solution
The estimate should occur at the "Lowest" level of the Work Breakdown Structure (WBS). This is because the lowest level of the WBS, also known as the work package level, provides the most detailed and accurate cost information. This level of detail allows for more precise budgeting and better cost control.
Similar Questions
9. Which of the following is included in the total project budget but is not included in the cost performance baseline? A. Control accounts B. Work package estimates C. Contingency reserves D. Management reserves
Write a detailed answer on : The Estimate Committee.
Baseline project budgets are derived from ____________.Multiple choice question.time-phasing the work packagesestimating activity durationsthe organization's overall budget
15. You and several of your key team leader are really struggling with estimating the overall cost of the project. The most probable cause for this estimating difficulty can be attributed to:A. Initial poor scope definitionB. Lack of required resourcesC. Insufficient funds D. Problems with the overall schedule
Which piece of information below is included in a resource agreement?Effort estimatesTime estimatesDependenciesContingencies