Which of the following are used to calculate the standard quantity per unit of direct materials?Multiple select question.Direct materials requirements per unit of finished product.Allowance for normal scrap and spoilage.Freight and transportation costs.

Question

Which of the following are used to calculate the standard quantity per unit of direct materials?Multiple select question.Direct materials requirements per unit of finished product.Allowance for normal scrap and spoilage.Freight and transportation costs.

🧐 Not the exact question you are looking for?Go ask a question

Solution

The standard quantity per unit of direct materials is calculated using:

  1. Direct materials requirements per unit of finished product: This refers to the amount of direct materials that are required to produce one unit of the finished product. It is calculated by dividing the total amount of direct materials used by the number of units produced.

  2. Allowance for normal scrap and spoilage: This refers to the amount of materials that are expected to be wasted or spoiled during the production process. It is calculated by estimating the percentage of materials that are typically wasted or spoiled and applying this percentage to the direct materials requirements per unit of finished product.

Freight and transportation costs are not used to calculate the standard quantity per unit of direct materials. These costs are considered part of the overhead costs, not the direct materials costs.

This problem has been solved

Similar Questions

Multiple Choice QuestionThe formula to determine the materials to be purchased isMultiple choice question.(units to produce divided by materials required for each unit) plus desired ending materials inventory minus beginning materials inventory(units to produce times materials required for each unit) minus desired ending materials inventory plus beginning materials inventory(units to produce times materials required for each unit) plus desired ending materials inventory minus beginning materials inventory(units to produce divided by materials required for each unit) minus desired ending materials inventory plus beginning materials inventory

Assume for a firm that budgeted production for July and August is 180 000 and 200 000 units respectively. It takes half a kilogram of direct material to make one unit of finished product. Materials inventory is maintained at 10 per cent of the next month's budgeted production needs. If the 30 June inventory of materials was 9000 kg, how many kilograms of direct material should be purchased during July?

Material requirements plus an allowance for normal inefficiencies are added together to determine the   per unit of output for direct materials.

Multiple Choice QuestionThe formula to compute the budgeted direct labor cost isMultiple choice question.units to produce times direct labor required per unit divided by direct labor cost per hourunits to produce times direct labor required per unit times direct labor cost per hourunits to produce times direct labor required per unit plus direct labor cost per hourunits to produce divided by direct labor required per unit times direct labor cost per hour

All of the following are manufacturing costs except:Multiple choice question.direct materialsoffice salariesdirect laboroverhead costs

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.