elect the correct answerThe efficiency of Rohil is twice that of Sanjay and he can finish a work in 4h less than the time taken by Sanjay. If both of them work together they can finish the same work?Options3h8h8/3h4/3h

Question

elect the correct answerThe efficiency of Rohil is twice that of Sanjay and he can finish a work in 4h less than the time taken by Sanjay. If both of them work together they can finish the same work?Options3h8h8/3h4/3h

🧐 Not the exact question you are looking for?Go ask a question

Solution

Let's solve this step by step:

  1. Let's assume the time taken by Sanjay to finish the work alone is 'x' hours.

  2. Since Rohil is twice as efficient as Sanjay, he would take half the time taken by Sanjay to finish the work. So, Rohil takes 'x/2' hours to finish the work.

  3. According to the problem, Rohil takes 4 hours less than Sanjay to finish the work. So, 'x/2 = x - 4'. Solving this equation, we get 'x = 8'. So, Sanjay takes 8 hours to finish the work alone.

  4. Rohil, being twice as efficient, takes half the time, which is 4 hours.

  5. If they work together, their combined rate is the sum of their individual rates. The rate of Sanjay is 1 job per 8 hours (1/8 job/hour) and the rate of Rohil is 1 job per 4 hours (1/4 job/hour).

  6. So, their combined rate is 1/8 + 1/4 = 3/8 job/hour.

  7. Therefore, to complete 1 job, they would take 1 / (3/8) = 8/3 hours.

So, the correct answer is 8/3 hours.

This problem has been solved

Similar Questions

Rajesh can complete a job in 18 days. Rohit is 50% more skilled than Rajesh. Find the total time taken to do the same job when they both work together.

To do a certain work, the ratio of efficiency of A to that of B is 3 : 7. Working together, they can complete the work in 10.5days. They work together for 8 days. 60% of the remaining work will be completed by A alone in?Options6.5 days5.5days5 days4 days

If Ashok completes four-ninth of the work in 8 hours, how long will he take to complete twice the amount of work at half his efficiency?Question 19Answera.71 hrsb.72 hrsc.80 hrsd.70 hrs

when working alone A takes 24 more days than time taken by A and B together to finish certain work. If A is 50% more efficient than B, then find the time taken by B to finish the work alone.

Select the correct answerAmit can complete a piece of work in 16 days. Rohit can complete the same piece of work in 8 days. If both of them work together in how many days can they complete the same piece of work?Options4 2/5 days6 days12 days5 1/3days

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.