When monitoring the project schedule, which task is performed by the project team member?Records effort spent on tasks during the projectCompares actual time to complete a task to original time estimatesConsiders resource realignment if tasks are off-trackApproves change requests to hire more labor to complete tasks
Question
When monitoring the project schedule, which task is performed by the project team member?Records effort spent on tasks during the projectCompares actual time to complete a task to original time estimatesConsiders resource realignment if tasks are off-trackApproves change requests to hire more labor to complete tasks
Solution
The task performed by the project team member when monitoring the project schedule is recording the effort spent on tasks during the project. This involves keeping track of the time and resources used to complete each task. This information can then be used to compare actual time to complete a task to original time estimates and consider resource realignment if tasks are off-track. However, approving change requests to hire more labor to complete tasks is typically a responsibility of the project manager or another higher-level role, not a team member.
Similar Questions
As a project manager, you identify tasks to complete in a project. Who will you consult to create an accurate time estimate for each task?1 pointA project manager from a different teamThe sponsors of the projectTeam members working on the tasksThe project’s primary stakeholders
Which of the following must be done by project team members to assist the project manager in monitoring a project budget? Report the impact of completing a deliverableRecord effort continuously during the completion of a taskRecord the risks associated with the project tasksReport services provided by a vendor with a fixed bid contract
Which process in project schedule management involves identifying the specific tasks that the project team members and stakeholders must perform to produce the project deliverables?Group of answer choicesestimating activity durationssequencing activitiesdefining activitiesdeveloping the schedule
Which items should you track throughout the project execution phase? Select all that apply.1 pointKey decisions and changes to the projectProject costsIndividual team members’ schedulesProgress toward milestones
In project schedule management, the main goal of which process is to ensure that the project team has complete understanding of all the work they must do as part of the project scope so they can start scheduling the work?Group of answer choicesestimating activity durationsestimating activity resourcesdefining activitiescontrolling the schedule