Question 5Which scrum meeting is most likely to include stakeholders?1 pointSprint review.Daily standup/scrum.Sprint planning meeting.Sprint retrospective.
Question
Question 5Which scrum meeting is most likely to include stakeholders?1 pointSprint review.Daily standup/scrum.Sprint planning meeting.Sprint retrospective.
Solution
The Scrum meeting that is most likely to include stakeholders is the Sprint Review.
Here's why:
-
Sprint Review: This is a meeting at the end of each sprint where the team presents what they completed during the sprint. It's an opportunity for stakeholders to provide feedback and understand the progress of the project. Therefore, stakeholders are likely to be included in this meeting.
-
Daily Standup/Scrum: This is a short meeting for the development team to sync on what they did the previous day, what they plan to do today, and any blockers they have. It's typically not
Similar Questions
True or false: Meetings and artifacts promote Scrum pillars and involve all teams and stakeholders.1 pointTrueFalse
What is the purpose of sprint planning meetings in Agile development?To review past sprints and identify areas for improvementTo evaluate individual performance and provide feedbackTo allocate tasks to team members for the upcoming sprintTo conduct team-building activities and improve collaboration
Who should necessarily attend the Daily Standup Meeting?The Development TeamThe Scrum TeamThe Development Team and Product OwnerThe Development Team and Scrum Master
n your organization, who all are part of a Sprint Review Meeting?
What is the purpose of the Daily Scrum Meeting?