Select all that applyWhich of the following are true of activity-based costing? Multiple select question.With activity-based costing, each activity has an associated cost pool.In the ABC two-stage cost system, the first stage consists of activities.In the ABC two-stage cost system, the first stage consists of departments.With activity-based costing, there is a single cost pool represe
Question
Select all that applyWhich of the following are true of activity-based costing? Multiple select question.With activity-based costing, each activity has an associated cost pool.In the ABC two-stage cost system, the first stage consists of activities.In the ABC two-stage cost system, the first stage consists of departments.With activity-based costing, there is a single cost pool represe
Solution
The correct answers are:
- With activity-based costing, each activity has an associated cost pool.
- In the ABC two-stage cost system, the first stage consists of activities.
Explanation:
Activity-based costing (ABC) is a method of assigning overhead and indirect costs—such as salaries and utilities—to products and services. The ABC system of cost accounting is based on activities, which is any event, unit of work, or task with a specific goal.
In the ABC system, each activity has an associated cost pool. This means that all costs associated with a specific activity are grouped together in a 'pool'. This cost pool is then used to allocate costs to products or services based on the amount of that activity they require.
The ABC system is a two-stage cost system. The first stage consists of activities. This is where costs are assigned to activities. The second stage is where these costs are allocated to the products or services that use these activities.
The statement "In the ABC two-stage cost system, the first stage consists of departments" is incorrect. In the ABC system, the first stage consists of activities, not departments.
The statement "With activity-based costing, there is a single cost pool" is also incorrect. In the ABC system, each activity has its own cost pool. There isn't a single cost pool representing all activities.
Similar Questions
Select all that applyWhich of the following are true of activity-based costing?Multiple select question.Activity-based costing is based on the concept that products consume activities and activities consume resources.Activity-based costing uses a single cost pool for the entire plant.Activity-based costing is a two-stage product costing method.Activity-based costing is a single-stage product costing method.
Fill in the Blank QuestionFill in the blank question.In activity-based costing, activities in each cost pool should be (similar / dissimilar) .
Facility-level activities and costs are considered product costs in activity-based costing.Select one:TrueFalse
Multiple Choice QuestionThe first step in applying activity-based costing isMultiple choice question.allocating overhead costs to cost objects.identifying the activities.compute rate for each activity.
The final step in the activity-based costing system is to Blank______.Multiple choice question.identify the activitiesidentify the cost driver(s)compute a cost driver rateassign the activity costs to products
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.