Fill in the Blank QuestionFill in the blank question.A company sells 800 units at $16 each, has variable costs of $12 per unit, and fixed costs of $1,200. Income is $.

Question

Fill in the Blank QuestionFill in the blank question.A company sells 800 units at 16each,hasvariablecostsof16 each, has variable costs of 12 per unit, and fixed costs of 1,200.Incomeis1,200. Income is .

🧐 Not the exact question you are looking for?Go ask a question

Solution

To solve this, we first need to calculate the total revenue and the total variable costs.

Step 1: Calculate total revenue The total revenue is calculated by multiplying the number of units sold by the price per unit. In this case, the company sells 800 units at 16each,sothetotalrevenueis80016 each, so the total revenue is 800 * 16 = $12,800.

Step 2: Calculate total variable costs The total variable costs are calculated by multiplying the number of units sold by the variable cost per unit. In this case, the variable cost per unit is 12,sothetotalvariablecostsare80012, so the total variable costs are 800 * 12 = $9,600.

Step 3: Calculate income The income is calculated by subtracting the total variable costs and the fixed costs from the total revenue. In this case, the fixed costs are 1,200,sotheincomeis1,200, so the income is 12,800 - 9,6009,600 - 1,200 = $2,000.

So, the income is $2,000.

This problem has been solved

Similar Questions

Fill in the Blank QuestionFill in the blank question.A company produces a product with variable costs of $2.50 per unit. The product sells for $5.00 per unit. The company has fixed costs of $3,000 and desires a target income of $10,000. The sales level in dollars to achieve the desired target income is $.

Based on a predicted level of production and sales of 22,000 units, a company anticipates total variable costs of $99,000, fixed costs of $30,000, and operating income of $36,000. Based on this information, the budgeted amount of fixed costs for 20,000 units would be:Group of answer choices$99,000.$90,000.$66,000.$30,000.$150,000.

At a production level of 5,600 units, a project has total costs of $89,000 and a variable cost per unit of $11.20. What is the amount of the total fixed costs?

If you know that total fixed cost is $200, total variable cost is $600, and total product is 4 units, then average total cost must be

If you know that total fixed cost is $200, total variable cost is $600, and total product is 4 units, then average total cost must beMultiple Choice$200.$250.$800.$3,200.

1/3