Knowee
Questions
Features
Study Tools

Xavier started a work and left after working on it for 4 days. Pakalu completed the remaining work in 18 days. Had Xavier worked for 6 days, Pakalu could have completed the remaining work in next 12 days. If both of them were asked to work on a similar kind of 'work', in how many days can they together complete the work?

Question

Xavier started a work and left after working on it for 4 days. Pakalu completed the remaining work in 18 days. Had Xavier worked for 6 days, Pakalu could have completed the remaining work in next 12 days. If both of them were asked to work on a similar kind of 'work', in how many days can they together complete the work?

🧐 Not the exact question you are looking for?Go ask a question

Solution

To solve this problem, we first need to understand the concept of work and efficiency in time and work problems.

  1. Xavier works for 4 days and Pakalu completes the remaining work in 18 days. This means the total work is equivalent to 4 days of Xavier's work + 18 days of Pakalu's work.

  2. In the second scenario, Xavier works for 6 days and Pakalu completes the remaining work in 12 days. This means the total work is also equivalent to 6 days of Xavier's work + 12 days of Pakalu's work.

Since the total work is the same in both scenarios, we can set these two equations equal to each other:

4X + 18P = 6X + 12P

Solving this equation for X (Xavier's work rate), we get:

X = 2P

This means Xavier's work rate is twice as fast as Pakalu's.

  1. Now, let's find the time it takes for them to complete the work together. We know that Xavier's work rate is twice as fast as Pakalu's, so let's denote Xavier's work rate as 2x and Pakalu's work rate as x.

The total work can be represented as 4 days of Xavier's work + 18 days of Pakalu's work, or 4(2x) + 18x = 26x.

If they work together, their combined work rate is 2x + x = 3x.

So, the time it takes for them to complete the work together is the total work divided by their combined work rate, or 26x / 3x = 26/3 ≈ 8.67 days.

Therefore, Xavier and Pakalu can together complete the work in approximately 8.67 days.

This problem has been solved

Similar Questions

A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in :8 days10 days12 days15 days

Ajith can do a piece of work in 10 days and Vijay can do the same work in 15 days. They started the work together but after 6 days Ajith left. Find, in how many days Vijay can complete the remaining work.

X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him until the completion of the work. How long did the work last?

A can do a piece of work in 8 days and B can do the same work in 10 days. They started the work together but after 3 days, A left . In how many days B can complete the remaining work?4 days7 days7.5 days3. 25 days

A and B can finish a work, working on alternate days, in 17 days, where A works on the first day. Similarly, they can finish the work, working on alternate days, in days, where B works on the first day. If C, working alone, can complete the work in 35 days, in how many days can the work be completed when A, B and C work together

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.