Multiple Choice QuestionXYZ Company makes one product and has calculated the following amounts for direct labor: AH x AR = 84,000;AHxSR=84,000; AH x SR = 83,000; SH x SR = 85,000.Computethelaborefficiencyvariance.Multiplechoicequestion.85,000. Compute the labor efficiency variance.Multiple choice question.1,000 U2,000F2,000 F2,000 U$1,000 F

🧐 Not the exact question you are looking for?Go ask a question

Solution

The labor efficiency variance is calculated as follows:

Labor Efficiency Variance = (Standard Hours - Actual Hours) x Standard Rate

From the given information, we can derive the following:

AH x AR = 84,000(ActualHoursxActualRate)AHxSR=84,000 (Actual Hours x Actual Rate) AH x SR = 83,000 (Actual Hours x Standard Rate) SH x SR = $85,000 (Standard Hours x Standard Rate)

We can find the Standard Rate (SR) by dividing the total cost at standard hours by the standard hours. However, we don't have the actual values for standard hours (SH) and actual hours (AH).

But we can use the given equations to find the labor efficiency variance.

The difference between (AH x SR) and (SH x SR) will give us the labor efficiency variance.

So, Labor Efficiency Variance = AH x SR - SH x SR = 83,00083,000 - 85,000 = -$2,000

The negative sign indicates that it is unfavorable. So, the labor efficiency variance is $2,000 Unfavorable.

So, the correct answer is "$2,000 U".

This problem has been solved

Similar Questions

Multiple Choice QuestionABC Company has set the following standards for one unit of product: Direct materials: 0.5 pounds @ $1.00 per pound; Direct labor: 1 hour @ $10.00 per hour. The company produced 35,000 units and had the following actual costs: Direct materials: 18,000 pounds at a total cost of $17,280; Direct labor: 36,000 hours at a total cost of $374,400. Compute the labor efficiency variance.Multiple choice question.$14,400 F$10,000 F$10,000 U$14,400 U

Given the following information, calculate the direct labor efficiency variance.  Actual production in units17,000Standard labor cost per unit1/2 hour @ $20 per hourActual cost for labor$216,750 for 12,750 hoursMultiple choice question.$85,000 unfavorable$46,750 favorable$46,750 unfavorable$85,000 favorable

Multiple Choice QuestionXYZ Company makes a product and has calculated the following amounts for direct materials: AQ x AP = $150,000; AQ x SP = $145,000; SQ x SP = $152,000. Compute the direct materials quantity variance.Multiple choice question.$5,000 U$7,000 U$5,000 F$7,000 F

ABC Company has set the following standards for one unit of product: Direct materials: 0.5 pounds @ $1.00 per pound; Direct labor: 1 hour @ $10.00 per hour. The company produced 35,000 units and had the following actual costs: Direct materials: 18,000 pounds at a total cost of $17,280; Direct labor: 36,000 hours at a total cost of $374,400. Compute the labor efficiency variance.Multiple choice question.$10,000 U$14,400 U$10,000 F$14,400 F

1/1

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.