Iterative waterfall modelOptions :provides feedback path to previous phase except development phasenever provides feedback path to previous phaseprovides feedback path to previous phase except feasibility study phasenone of above

Question

Iterative waterfall modelOptions :provides feedback path to previous phase except development phasenever provides feedback path to previous phaseprovides feedback path to previous phase except feasibility study phasenone of above

🧐 Not the exact question you are looking for?Go ask a question

Solution

The iterative waterfall model provides a feedback path to the previous phase. This means that after each phase, the results are reviewed and if there are any issues, the project can revert back to the previous phase for correction. However, this model does not provide a feedback path to the feasibility study phase. This is because the feasibility study is the first phase of the project, where the basic requirements and resources are determined. If there are any issues in the later phases, they cannot be corrected by going back to the feasibility study phase. Therefore, the correct option is "provides feedback path to previous phase except feasibility study phase".

This problem has been solved

Similar Questions

The classical waterfall modelOptions :never provides feedback path to previous phasesmay or may not provides feedback path to previous phasesalways provides feedback path to previous phasesnone of above

Which of these characteristics of the Waterfall model  inhibits flexibility during the development process?Iterative approachFrozen deliverables for each phaseContinuous integrationAgile methodology

Question 2The Waterfall approach relies on phases such as _____.1 pointAnalyzing problems, clarifying processes, and implementing changesPair negotiations, unit testing, and simplicityVisualization, work in progress, and tracking flowDesigning, coding, and testing

In the Waterfall model, which phase comes immediately after the Design phase?Question 3Select one:a.Implementationb.Testingc.Maintenanced.Planning

In the Waterfall model, which phase comes after the testing phase?