Multiple Choice QuestionThe earned value system uses time-phased costs to enable comparisons between actual and planned ____ and ____.Multiple choice question.scope; schedulecost; riskschedule; costs

Question

Multiple Choice QuestionThe earned value system uses time-phased costs to enable comparisons between actual and planned ____ and ____.Multiple choice question.scope; schedulecost; riskschedule; costs

🧐 Not the exact question you are looking for?Go ask a question

Solution

The correct answer is: schedule; cost.

The Earned Value System is a project management technique that measures the performance of a project. It compares the amount of work that was planned to be done by a certain time (planned value) with what was actually accomplished (earned value) in terms of cost. Therefore, it enables comparisons between actual and planned schedule and cost.

Similar Questions

Multiple Choice QuestionIn the cost/schedule system, when computing cost variance and schedule variance, ____ status reports are prepared for each level of management.Multiple choice question.verbalhierarchicalidentical

Multiple Choice QuestionWhich are appropriate methods for handling cost risk?Multiple choice question.Item-by-item price risk analysisReducing project durationLump sum approachBack-up or alternate plans

Multiple Choice QuestionThe standard overhead rate is computed separately for:Multiple choice question.product and period costsfixed and variable costsdirect and indirect costs

Multiple Choice QuestionWhat do market value calculations determine?Multiple choice question.They determine the specific monetary value of employee benefits.They determine the value of the health care based on future calculations of health care needs.They determine an approximation of the monetary value of employee benefits.They determine the health care costs based on changing market values of health care.

The current status of a project is that cost variance (CV) is -$100. This means the project is ___.Multiple choice question.over budgetunder budgetbehind scheduleahead of schedule