Which value for TCPI indicates the project is under budget?Multiple choice question.0.781.001.78
Question
Which value for TCPI indicates the project is under budget?Multiple choice question.0.781.001.78
Solution
The To-Complete Performance Index (TCPI) is a measure of the efficiency at which resources on the project should be used for the rest of the project.
If the TCPI is less than 1, it means the project is under budget. So, in this case, the value 0.78 indicates the project is under budget.
Similar Questions
As a project manager, what does going under budget on a project indicate about your approach to budget management? Select all that apply.1 pointThat you effectively conserved funds and will likely receive larger budgets for future projectsThat you could have spent more on the project to provide extra resourcesThat you accurately estimated the total cost of ownership (TCO) That your initial estimates were inaccurate
9. Which of the following is included in the total project budget but is not included in the cost performance baseline? A. Control accounts B. Work package estimates C. Contingency reserves D. Management reserves
The current status of a project is that cost variance (CV) is -$100. This means the project is ___.Multiple choice question.over budgetunder budgetbehind scheduleahead of schedule
A PCIB of 0.75 would mean ___.Multiple choice question.actual cost to date is 75% of the estimated total cost at completion.the project is over budget by 75%.the work accomplished to date represents 75% of the total budgeted dollars for the project.
Question 3As a project manager, the project sponsor gives you cost estimates with a set amount of money to spend. What challenge for effective budgeting does this represent?1 pointInsufficient cash flowLack of historical dataPre-allocated budgetScope creep
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.