Question 4As a Product Owner, you set the initial Sprint duration the team has to work on their items. This refers to what Scrum concept? 1 pointTimeboxIntervalTime frameSchedule
Question
Question 4As a Product Owner, you set the initial Sprint duration the team has to work on their items. This refers to what Scrum concept? 1 pointTimeboxIntervalTime frameSchedule
Solution
The Scrum concept referred to in the question is "Timebox". In Scrum, a timebox is a defined, fixed period of time during which a specific activity takes place. For the Product Owner setting the initial Sprint duration, this is the timebox for the team to work on their items.
Similar Questions
Which of the following factors should you consider when setting the length of a Sprint’s timebox? Select all that apply.1 pointThe likelihood that the project will go over budgetHow much overhead—such as testing and review—goes into the delivery of the productThe expected frequency of changesHow much focused time the solution Developers need to build a Backlog item
The time box for the Sprint Planning event is?8 hours for a monthly sprint. For shorter sprints, it is usually shorter4 hoursWhenever it is doneMonthly
Question 3How long is a typical Sprint’s timebox?1 pointBetween one and three daysBetween one and four weeksBetween two and three months
A framework that uses fixed-length iterations, called sprints, usually lasting 2-4 weeks. Scrum teams have defined roles (e.g., Scrum Master, Product Owner) and hold regular ceremonies (e.g., daily stand-ups, sprint planning, sprint review, and retrospectives).
What long-term objective for the Scrum Team is included in the Product Backlog? 1 pointProduct requirements documentProduct GoalProduct OwnerSprint Goal